Costs lower for Vares silver project
PERTH (miningweekly.com) – An updated definitive feasibility study (DFS) for the Vares silver project, in Bosnia & Herzegovina, has seen capital costs decline while the project’s net present value (NPV) and internal rate of return (IRR) have increased.
ASX-listed Adriatic Metals this week reported that an updated capital cost estimate for the Vares silver project had estimated that the project would require a $168-million investment, compared with the $173-million estimated in the 2020 DFS.
The updated DFS has also increased the project’s post tax NPV from the $1.04-billion reported in the original DFS to $1.06-billion, while the IRR has increased from 113% to 134%.
The pay-back period has declined from 1.2 years to 0.7 years, while the project’s all-in sustaining cost estimates have declined from $9.70/oz to $7.30/oz of silver.
“The completion of the 2021 DFS is a major milestone for the company, and clearly demonstrates the exceptional potential of the Vares silver project,” said Adriatic MD and CEO Paul Cronin.
“Project delivery and execution risks have been substantially reduced through the simplification of the process flowsheet and initial capital costs lowered against the backdrop of inflationary construction costs, whilst improving the overall project economics. In the design of this project, environmental and economic sustainability have been at the core of our thinking, shaping the project to ensure that its economic and environmental benefits extend well beyond the current mine life, and provide a perpetual benefit to our local community in Vares and indeed, to the BiH economy.”
Cronin said that the company’s focus would now be on finalising project financing, which is well advanced, and concurrently starting constructio,n while continuing to look for marginal improvements in metallurgical recovery, and capital and operating costs.
“Additionally, we have commenced a study to expand the renewable energy production we have at the Vares processing plant, and [to] augment that capacity to ensure that the Vares silver project reduces its carbon emissions significantly, soon after the commencement of commercial production. As demonstrated in our recent exploration results, we are confident that we can expand the resources and reserves at the Vares project and look forward to working with the Vares community for decades to come, jointly demonstrating the benefits of mining operations in a European context.”
Comments
The
content
you are trying to access is only available to subscribers.
If you are already a subscriber, you can Login Here.
If you are not a subscriber, you can subscribe now, by selecting one of the below options.
For more information or assistance, please contact us at subscriptions@creamermedia.co.za.
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation