https://www.miningweekly.com

Cape Town runway project awaiting Economic Regulator approval

24th November 2023

By: Tasneem Bulbulia

Senior Contributing Editor Online

     

Font size: - +

The starting of the Cape Town Aviation Infrastructure runway realignment is dependent on approval by the Economic Regulator, which is outstanding at this point, as well as a review of the masterplan and consultation with the industry to ensure its business-case viability within the context of the revised traffic forecasts and other relevant criteria, the Department of Transport (DoT) has noted in a reply to questions at the National Council of Provinces.

The project, when approved, will follow a tender process as regulated in the Preferential Procurement Policy Framework Act.

At this point, the project is not part of Airports Company South Africa’s (ACSA’s) immediate plans and has not been approved as yet by the Economic Regulator, the DoT said.

In response to the question of “why two runways are sacrificed to provide for one new runway”, the DoT said this was to free up space for apron and terminal development west of the current main runway 01/19, in accordance with the approved Airport Master Plan.

The current passenger terminal area is landlocked between the current runway and the airport surface access system. No space therefore exists to expand the capacity of the airport, it explained.

Moreover, the DoT said the current peak capacity of the existing runway is limited at 30 movements (landings and take-offs) hourly owing to the lack of a parallel taxiway as there is no space to build a parallel taxiway.

The new proposed runway will provide a peak capacity of 42 to 44 movements hourly to accommodate future traffic demand. All these factors are under review prior to ACSA making a revised investment decision.

The current runway 16/34 was proposed to be removed as the proposed new runway 18/36 and associated taxiways will be built over the current secondary runway. The current main runway 01/19 will not be removed and will be used as a taxiway until there is space required for aircraft stands and terminal buildings in the long term, the DoT outlined.

During the preparation of the Airport Master Plan, six runway options were considered and, through a technical multicriteria assessment, it was recommended to realign the current main runway, the department notes.

Another question posed was whether runway 16/34 will be improved for cross runway operations should the plan not be implemented. The DoT said this would have no operational benefits.

All aspects of the project would be introduced at a rate consistent with traffic demand and ACSA’s affordability.

Responding to the Democratic Alliance (DA), Transport Minister Sindisiwe Chikunga said the duration of the construction period for Cape Town Aviation Infrastructure was unknown at this stage, as the project was still being considered by the Economic Regulator.

Once approval was received, ACSA would finalise the appropriate project implementation plan.

The DA also questioned whether Chikunga and/or her department had considered the possibility of building a new fully instrument-conditioned equipped airport in the Kalbaskraal area.

“The planned runway realignment project is further intended to increase the capacity of the airport. “Considering the existing demand of air travel within the greater Cape Town area, there is currently no compelling need to construct a new airport in the Kalbaskraal area.

“Furthermore, ACSA’s Recover and Sustain Strategy and the Economic Regulator permission process has identified a new process for Infrastructure Capital Programme funding in line with the traffic projections, and restoration of some of the capacity projects over the next five or ten years,” Chikunga explained.

She said the construction of an airport in the Kalbaskraal would have a detrimental impact on the airspace capacity and safety of operations of Cape Town International Airport, and that Kalbaskraal could not be an alternative airport.

The DA also questioned whether Chikunga had considered transferring the use of buildings on the eastern side of the main runway that were previously used by the South African Air Force, and are now being used by the South African Police Service, to ACSA for use by General Aviation (GA) at a historically equivalent rate to provide quick access to the runway infrastructure to relieve congestion on the taxiways to assist GA in more effective use of spare capacity.

In response, the Minister said the implementation plan for the runway project had not been finalised as the approval had not been granted. After such decision from the Economic Regulator, the implementation plan, including the impact on surrounding areas, will only then be developed, she explained.

The DA also queried the feasibility of making the Somersveld Airfield, which is currently under military control, available for GA use.

Chikunga explained that military airports are a competence of the South African National Defence Force (SANDF); however, the 2017 National Civil Aviation Policy (NCAP) recommended co-use of military aerodromes with civilian traffic where possible. This requires approval being granted by the SANDF, as well as consultation with the South African Civil Aviation Authority.

She said Air Traffic Navigation Services does not object to the aerodrome being used for GA with an aerodrome traffic area of not more than 5 km around the aerodrome and also, not more than 1 500 feet above the aerodrome elevation.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION