Bunyu graphite project, Tanzania – update

13th October 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Bunyu graphite project.

Location
Tanzania.

Project Owner/s
Volt Resources.

Project Description
An updated prefeasibility feasibility study (PFS) has improved the economics of the Stage 1 project, based on a mining and processing plant of 400 000 t/y of ore producing on average 24 780 t/y of graphite products.

The updated PFS has estimated a capital cost of $33.1-million, compared with the $31.8-million estimated in the 2018 PFS, with the project’s net revenue increasing from $268.6-million to $433.2-million, its after-tax net present value from $14.7-million to $36.4-million and its internal rate of return from 19.3% to 23.6%.

The project’s mine life has also increased from 7.1 years, estimated in the original PFS, to nearly 14 years.

Potential Job Creation
Stage 1 has a pretax net present value, at a 10% discount rate, of $18.6-million and an internal rate of return of 21%, with a payback after tax of 4.4 years.

Net Present Value/Internal Rate of Return
The updated PFS delivers a pretax net present value of $58.9-million and an internal rate of return of 31.5%, with a payback period of 2.9 years.

Capital Expenditure
The updated PFS has estimated a capital cost of $33.1-million, compared with the $31.8-million estimated in the 2018 PFS.

Planned Start/End Date
Not stated.

Latest Developments
Volt Resources has signed a letter of intent (LoI) with US firm M2i Global Inc to supply up to 20 000 t/y of graphite to the US Department of Defence (DoD).

Under the LoI, M2i will attempt to secure a graphite procurement contract with DoD for up to 20 000 t/y of graphite for three years. Volt would deliver graphite of between 94% and 99.5% purity from its subsidiary Zavalievsky Graphite. If feasible, Volt will extend long-term supply of graphite from Bunyu Tanzania Phase 2 production for M2i customers.

“With the ability to supply natural flake graphite produced in Europe and future production from our Tanzania-based Bunyu graphite project, combined with battery anode material production technology advancing in the US, Volt offers future growth opportunities through the entire supply chain few graphite companies can match,” Volt executive chairperson Asimwe Kabunga has said.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Volt Resources, tel +61 8 9486 7788 or email info@voltresources.com.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION