Andromeda updates Great White economics

29th August 2023

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – An updated definitive feasibility study (DFS) into the Great White kaolin project, in South Australia, has increased the expected revenue and net present value estimates while decreasing capital cost expectations.

ASX-listed Andromeda Metals this week reported that based on the 300 000 t/y kaolin production target, the updated DFS has increased the project’s estimated net present value from the A$613-million considered in the 2022 DFS, to A$1.01-billion.

Revenue projections have increased by 32%, from A$4.7-billion to A$6.2-billion, while the internal rate of return has increased from 36% to 45%. Capital cost for the project has dropped by 9%, from A$207-million to A$188-million, with the pay-back period decreasing by 14% from 5.9 years to 5.1 years.

The project’s expected mine life has remained unchanged at 28 years, based on an ore reserve of 15.1-million tonnes.

“The 2023 DFS represents the outcome of a rigorous commercial and business strategy review for commercialising our construction-ready project, to meet rising market demand,” said Andromeda CEO and MD Bob Katsiouleris.

“As we move to finalising debt funding, the 2023 DFS will underpin our funding strategy for the remaining capital required to move towards anticipated construction and into production.”

Subject to additional funding, the commercial strategy review identified an opportunity for high-purity alumina (HPA) to become part of Andromeda’s complementary product portfolio. Technical and market validation is proposed to restart, post the commissioning of Great White.

It is estimated A$8-million to A$10-million will be required to complete a prefeasibility study on HPA, the commercialisation of which is not included in the 2023 DFS.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION