Witwatersrand basin project – Qala Shallows Stage 1, South Africa – update

Image of gold nuggets

Photo by Bloomberg

14th January 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Witwatersrand basin project (WBP) – Qala Shallows Stage 1.

Location
At the northern edge of the Witwatersrand basin, in the Central Rand Goldfield, immediately south-west of the City of Johannesburg, in Gauteng, South Africa.

Project Owner/s
West Wits Mining.

Project Description
Qala Shallows is Stage 1 of 5 of West Wits Mining’s WBP, with Qala Shallows representing an estimated 40% of the total planned production of the total potential of the WBP1.

The project has a substantial maiden ore reserve of three-million tonnes grading 2.88 g/t gold, which includes a proven ore reserve of 830 000 t.

The definitive feasibility study (DFS) completed on the Qala Shallows supports the development of an underground mining operation with a robust rate of return over a 17-year life-of-mine.

The reefs to be processed during the life of the project are the two Kimberley reefs, K9A and K9B. The Kimberley reef is a free milling ore containing minor quantities of sulphides, mainly pyrite.

The Qala Shallows has the potential to ramp up to run-of-mine steady-state production of about 53 000 oz/y and peak production of 60 000 oz/y.

The DFS has shown that conventional breast mining in an underhand configuration is the optimal method for the deposit.

First ore is expected to be extracted 12 months from the  start of development, building up to an annualised production of 25 000 oz/y of gold after 30 months, and reaching full steady-state production of 53 000 oz/y of gold after Year 4.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
At a gold price of $1 750/oz, the project has a pretax net present value, at a 7.5% discount rate, of $151-million and an internal rate of return of 35%, with a payback of 5.5 years.

Capital Expenditure
The project requires peak funding of about $50-million.

Planned Start/End Date
Development of the project is planned to start in September 2021.

Latest Developments
The project is on track for early production in February 2022.

West Wits Mining reported in December 2021 that key site infrastructure had been completed, including diesel and power supply, potable and service water, security fences and offices.

The Qala adit boxcut construction and rehabilitation, brow and adit support are nearing completion.

Qala Shallows secondary access, the 12E Winze shaft and rehabilitation for early access have been completed, consequenlty allowing for the sampling and surveying of extended areas of underground workings.

Decline production equipment has been delivered and commissioned, including a ten-tonne load, haul-and-dump, twin boom drill rig, as well as a utility vehicle.

Key Contracts, Suppliers and Consultants
Bara Consulting (DFS) and Modi Mining (early mining initiative’s activities) and Siyabhowa-Humba Joint Venture (civil contractor – supply and install surface bulk supply infrastructure to offices and underground workings).

Contact Details for Project Information
West Wits Mining, tel +61 3 8692 9049 or email info@westwitsmining.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Lilak Aluminium
Lilak Aluminium

For over 15 years, Lilak Aluminium, a trusted leader in architectural extrusion supply, has delivered excellence to businesses like yours.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.049 0.957s - 111pq - 2rq
Subscribe Now