Waterval smelter cogeneration plant, South Africa
Name and Location
Waterval smelter cogeneration plant, North West, South Africa.
Client
Eternity Power, a special purpose vehicle that is 80% owned by Investec Corporate and Institutional Banking and 20% owned by clean-energy project developer Vuselela Energy.
Project Description
The project involves the construction of South Africa’s first cogeneration power plant using an Ormat Organic Rankine Cycle system, which uses waste received from a smelter to evaporate organic liquid and drive an expansion turbine.
The first turbine will be implemented by Anglo American Platinum and will be used to supply its Waterval smelter in Rustenburg, in the North West.
The plant’s gross installed capacity will be 4.9 MW, but is expected to run at an average rate of 3.2 MWh, depending on the available heat load.
A year from now the facility is expected to generate 20 GWh.
Value
The project will cost R155-million. Investec is providing R105-million, funded through debt, while an additional R30-million is being funded through an infrastructure grant from the Department of Trade and Industry. The balance is being funded through equity.
Duration
Construction of the cogeneration facility is expected to be completed by June 2014.
Latest Developments
Ormat Technologies has been selected as Eternity Power’s technology partner and will provide the equipment to convert thermal energy into electrical energy.
Key Contracts and Suppliers
Ormat Technologies (technology partner).
On Budget and on Time?
Not stated.
Contact Details for Project Information
Investec, tel +27 11 286 7000 or +27 11 286 7777.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation