Waterberg Joint Venture, Palladium and Platinum project, South Africa

21st August 2015

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Waterberg Joint Venture (JV), Palladium and Platinum project, Limpopo, South Africa.

Client
The  prior Waterberg JV and  Waterberg Extension Projects have  been consolidated into a unitised project area now known as the Waterberg Joint Venture (JV). The transaction includes a firm $20-million funding commitment from JV partner Japan Oil, Gas, Metals National Corporation (JOGMEC) over the next three years.

The JOGMEC-funded budget to March 31, 2016, is $8-million for the entire new Waterberg JV, including fill-in drilling, extension exploration drilling and prefeasibility engineering.

PTM will increase its direct and indirect effective interest in the old Waterberg JV area from its current 49.98% to 58.62%, comprising 45.65% held directly and 12.97% held indirectly through Mnombo. PTM will decrease its effective interest in the old Waterberg Extension from 87% to 58.62%. Jogmec will decrease its interest in the old Waterberg JV from 37% to 28.35% and increase its interest in the old Waterberg Extension from zero to 28.35%. Mnombo will hold 26% of the new Waterberg JV project.

PTM has noted that the exchange of interests are "ounce neutral" in that each party is exchanging the same number of inferred resource ounces.

PTM will retain the responsibility of operating the consolidated project and has achieved a majority effective interest in the overall project.

Project Description
The Waterberg deposit consists of discrete, layered and continuous platinum group metal- (PGM-) bearing layers, starting at 140 m from the surface, with a consistent westerly dip. The deposit has so far been drilled for about 10.4 km northwards on strike. Geophysical surveys and drilling, to date, indicate that the deposit remains open down dip and on strike to the north-west.

Net Present Value/Internal Rate of Return
Not stated.

Value
Not stated.

Duration
A prelimnary economic assesment for the original Waterberg JV was completed in June 2014. A prefeasibility study is under way with expected completion in late in the 2015/early 2016 calendar year.

Latest Developments
PTM has increased the resource estimate for platinum, palladium and gold (3E) at the Waterberg JV project, expanding the inferred resource and improving the confidence in previous results.

Effective July 20, 2015 the mineral resources at Waterberg on a 100% project basis has risen to an estimated 25.64-million ounces of 3E in the inferred category, in addition to 12.61-million ounces of 3E in the indicated category.

The inferred resource comprises 246-million tonnes grading 3.25 g/t 3E (0.98 g/t platinum, 2.11 g/t palladium and 0.16 g/t gold at a 2.5 g/t cutoff). The indicated resource comprises 121-million tonnes grading 3.24 g/t 3E (0.97 g/t platinum, 2.11 g/t palladium and 0.16 g/t gold).

Meanwhile, ten drill rigs are currently active at the Waterberg project. The deposit remains open for expansion. JV partner Japan Oil, Gas and Metals National Corporation (Jogmec) is funding drilling and engineering work under a $20-million firm commitment to the JV.

PTM has reported that the shallowest T-zone intersection is at 140 m below surface. The current drill programme is designed to expand the shallow T-zone resource for prefeasibility planning. Super F-zones within the resource, where thickness exceeds 15 m, are also a focus of current drilling.

The thicker zones have the potential to add significantly to early mine plans for bulk mining methods being considered in the ongoing prefeasibility study (PFS).

The PFS is being completed by project teams from global independent mining engineering firm DRA, along with PTM, on behalf of the Waterberg JV. Metallurgical work, plant designs, metal marketing studies, costing, engineering, servitude layouts for water and power and project planning are advancing as drilling continues for further resource expansion and definition.

Prefeasibility work on the overall project is progressing, with budget quotations currently in progress for the delivery of bulk services of electricity and water and upgraded roads.

Metallurgical results completed by DRA have generally confirmed earlier work completed as a component of an earlier preliminary economic assessment at Waterberg. Samples have been analysed using grinding and flotation tests and have provided about 80% recovery with a 100 g/t concentrate on the F-zone.

Further optimisation and flow sheet design work is also proceeding.

PTM has indicated that the Waterberg material shows an “encouraging flotation response", producing a saleable clean concentrate final product.

Key Contracts and Suppliers
WorleyParsons (PEA); DRA (qualified person role for the ongoing Waterberg prefeasibility study) and Coffey Mining (South Africa)(independent resource assessment).

On Budget and on Time?
The project has continued to expand and operations have been within budget. The PFS is expected to be completed in late 2015/early 2016.

Contact Details for Project Information
PTM, tel +27 11 782 2186, fax +27 11 782 4338 or email info@platinumgroupmetals.net.
Jogmec public relations division, tel +81 3 6758 8106.
WorleyParsons, tel +27 11 218 3000 or fax +27 11 218 3100.
DRA, tel +27 11 202 8600 or email info@DRAglobal.com.
Coffey Mining (South Africa), tel +27 11 679 3331 or fax +27 11 679 3272

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sweet-Orr
Sweet-Orr

Sweet-Orr, established in 1871, is a global leader in superior protective workwear, known for quality, innovation, and performance.

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.046 0.786s - 111pq - 2rq
Subscribe Now