https://www.miningweekly.com

Tropicana on schedule for Dec Q start

31st January 2013

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) - Gold miner AngloGold Ashanti on Thursday said that its 70%-held Tropicana project, in Western Australia, remained on schedule to start production during the December quarter of this year, albeit at a higher cost.

In a statement to shareholders, the miner noted that gold production for the first three years remained in the range of between 470 000 oz/y and 490 000 oz/y. However, cash costs for the operation had increased slightly, owing to the reduction in fuel rebates associated with the introduction of a carbon tax.

At approval, the Tropicana project had a mine life of ten years, with recent exploration success extending this to more than 11 years. The project currently has a mineral resource of 118-million tons, grading 1.08 g/t for 7.89-million ounces of gold.

At a 100% project basis, the project would require a capital investment of between A$820-million and A$845-million, which was an 11% increase on the mid-point of the capital range forecasted at the time of project approval.

AngloGold CEO Mark Cutifani attributed the higher forecast to significant increases in construction labour costs, and decreased productivity, which had resulted in higher on-site labour requirements.

However, he noted that this increase was in line with additional contingencies, and added that the new capital estimates were consistent with the top-end cost range flagged at the time of approval.

“The West Australian construction market is overheated and this, along with extreme skills shortages, has impacted labour productivity and, subsequently, costs.”

Cutifani noted that progress to date had confirmed AngloGold’s confidence in the strength of the Tropicana project, and exploration continued to deliver the upside the company believed was present at approval.

“Pre-commissioning will begin in the third quarter, leading to the start of production and production ramp-up in the fourth quarter,” he added.

The first phase of mining fleet mobilization was completed, and the contractor started mining ahead of schedule, with more than 3.3-million cubic metres mined by the end of 2012.

The next phase of mobilization was scheduled to start in February 2013.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

AQS Liquid Transfer
AQS Liquid Transfer

AxFlow AQS Liquid Transfer (Pty) Ltd is an Importer and Distributor of Pumps in Southern Africa

VISIT SHOWROOM 
ABB Electrification
ABB Electrification

Electrifying the world in a safe, smart, and sustainable way, ABB Electrification is a global technology leader in electrical distribution and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.045 0.568s - 111pq - 2rq
Subscribe Now