Name of the project and location
Sukari gold project, Egypt.

Project description
Centamin Egypt’s board of directors has approved the development of the Sukari gold project in Egypt following the completion of a definitive feasibility study (DFS).

The Sukari gold project consists of a 2,5-km-long porphyry granite hill, situated about 700 km south of Cairo and 25 km west of Marsa Alam on the Red Sea.

The base case DFS has concluded that a four-million-ton-a-year plant, producing on average 200 000 oz/y, over 15 years of mining, is economically robust.

The 8,26-million-ounce resource is not closed off and a ten-rig drilling programme is ongoing. Significant resource growth is expected and there is potential to increase the future production profile.

The Sukari gold project will be the first modern gold-mine operation in Egypt.

Value
Total capital construction costs are estimated at $216-million.

Duration
The project was given the go-ahead in February 2007. Commissioning is expected in the third quarter of 2008.

Breakdown of main contracts
Not stated.

Client
Centamin Egypt.

Latest developments
None stated.

Participants
None stated.

Will any structural steel be used and, if so, how much?
Not stated.

On budget and on time?
Too early to state.

Contact details for project information
Centamin Egypt, tel +618 9316 2640, fax +618 9316 2650 or email centamin@centamin.com.au .

 

Edited by Terence Creamer
Creamer Media Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Hanna Instruments (Pty) Ltd
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
Iritron
Iritron

Iritron delivers advanced automation, control, and optimisation solutions to the Mining, Minerals & Metals, Consumer Package Goods and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.046 0.613s - 111pq - 2rq
Subscribe Now