St Barbara expects Simberi to be cash positive by year end

St Barbara expects Simberi to be cash positive by year end

Photo by Bloomberg

25th March 2014

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – Gold miner St Barbara on Tuesday told shareholders that it expected to deliver about 11 000 oz of gold from its Simberi operation, in Papua New Guinea, during the three months to March.

For the full year, production was estimated at between 45 000 oz and 50 000 oz as the company worked to remedy Simberi’s poor mining performance and delays in ramping up the processing circuit.

St Barbara said that the project would likely be cash positive by December.

The Simberi operation has continually failed to meet its production expectations, and St Barbara was forced to make staff cuts at the operation in an effort to reduce operating costs.

A review was implemented to look at cost reductions and initiatives to lift operating performance, and to complete the commissioning of the oxide expansion from 2-million tonnes a year to 3.5-million tonnes a year.

The ASX-listed miner said on Tuesday that following the review process, the company had a better understanding of the technical issues faced at the project, and would implement a corrective work programme at minimal costs.

Additional low-hour used haul trucks were being procured to lift fleet reliability and a number of rebuilds of key mining equipment were also scheduled.

The recently completed processing plant expansion also required significant debottlenecking and optimisation work to achieve nameplate performance, the company said, adding that a scope of work had been clearly defined, and a punch list of rectification work was being closely managed.

St Barbara MD and CEO Tim Lehany told shareholders that the delay at Simberi was “very disappointing” but noted that the ramp-up to full capacity would be achieved.

“The substantial capital spend is behind us at Simberi and, once this rectification work is completed, I am confident that Simberi will be a valuable long-term asset,” he said.

By March next year, the project was expected to produce at a yearly rate of between 90 000 oz and 100 000 oz.

Edited by Mariaan Webb
Creamer Media Contract Publishing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Alcohol Breathalysers
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.047 0.553s - 110pq - 2rq
Subscribe Now