Springvale coal mine extension project, Australia
Name and Location
Springvale coal mine extension project, New South Wales, Australia.
Client
Centennial Coal.
Project Description
The project involves the proposed expansion of the Springvale coal mine’s longwall mining operations further south, east and south-east.
The project will extract coal from 20 longwalls – LW416 to 432 and LW501 to 503 – and continued operations at the mine’s surface infrastructure site.
The main components of the project include:
• continued longwall mining operations to extract up to 4.5-million tonnes a year of run-of-mine (RoM) coal from the Lithgow seam over 13 years;
• continued operation of the mine’s top pit area, support facilities and utilities;
• the extension and continued use of the Springvale Delta water scheme, bore dewatering facilities and ventilation infrastructure;
• continued processing (sizing and screening) of RoM coal at the pit top area;
• continued stockpiling of RoM coal at 85 000 t capacity;
• continued exploration activities in EL6974 and A460;
• continued transportation of processed coal by overland conveyor to the Western Coal Services site for further processing or to the Mt Piper power station; and/or by road haulage to other local domestic customers (limited to 50 000 t/y); and
• the rehabilitation of the pit top area and Newnes plateau sites.
Net Present Value/Internal Rate of Return
Not stated.
Value
The project is estimated at $17.5-million.
Duration
Not stated.
Latest Developments
The mine life at the Springvale coal mine has been extended by 13 years after the New South Wales Planning Commission (PAC) approved Centennial’s extension plans.
The PAC review will now go to state and federal governments for approval and final determination.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Centennial Coal, tel +61 2 9266 2700, fax +61 2 9261 5533 or email info@centennialcoal.com.au.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation