Project Description
The optimised feasibility study envisages an initial ten-year mine life, including 6.5 years of underground mining, with strong early cashflow and a rapid payback of capital.

Four separate mineral resources have been estimated for the Sanbrado project comprising Mankarga 1 North, Mankarga 1 South, Mankarga 3 and Mankarga 5.

The current mineral resource is estimated at 39.4-million tonnes grading 1.9 g/t gold for 2.41-million ounces of gold in the indicated category, and 15.7-million tonnes grading 1.3 g/t gold for 680 000 oz of gold in the inferred category.

The project’s reserves have been updated to a probable ore reserve of 21.6-million tonnes grading 2.4 g/t gold.

The project comprises several openpits, all within 1 km to 2 km of the plant site, and an underground mine, accessed through a boxcut and a portal south-west of the M1 South openpit.

The processing plant comprises a conventional semiautogenous ball mill crusher milling circuit, as well as gravity and carbon-in-leach processing, with a nominal throughput capacity of 2.2-million tonnes a year.

Underground mining will be completed in Year 6 of gold production.

Openpit mining will continue until midway of Year 10 of production, with processing conducted for a full ten years.

Mining and processing of the high-grade M1 South probable ore reserve will be prioritised, generating significant early cashflow.

Sanbrado is expected to produce 301 000 oz in the first year of operations, with average yearly production expected to increase to 217 000 oz/y of gold over the first five years of the mine life, compared with 211 000 oz/y in the June 2018 feasibility study.

Production over the life-of-mine is estimated at 1.53-million ounces, compared with 1.46-million ounces in the June 2018 feasibility study.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The optimised feasibility study shows the project to have a pretax net present value, at a 5% discount rate, of $612-million (June 2018 feasibility study: $567-million) and an internal rate of return of 82.8%, with a payback of 14 months (June 2018 feasibility study: 16 months) following commissioning.

Capital Expenditure
Capital expenditure, including all openpit and underground preproduction mining and development costs, contingencies, duties and taxes, is estimated at $186-million (June 2018 feasibility study: $185-million).

Planned Start/End Date
First gold pour is scheduled for the third quarter of 2020.

Latest Developments
West African Resources processed the first underground ore at its Sanbrado gold project this month.

In March, the company poured its first gold at Sanbrado. The first underground development ore was also mined and stockpiled in March, and is ready for processing.

Key Contracts and Suppliers
None stated.

Contact Details for Project Information
West African Resources, tel +61 8 9481 7344 or email info@westafricanresources.com.

 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 
Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.041 0.948s - 111pq - 2rq
Subscribe Now