Pyramid Lake gypsum project, Australia
Name of the Project
Pyramid Lake gypsum project.
Location
Western Australia.
Client
Cohiba Minerals.
Project Description
The project entails the initial production of 50 000 t/y of gypsum, ramping up to 400 000 t/y.
The operation has a mine life of more than ten years, based on indicated and inferred resources.
The mine (essentially a quarry) will have a very simple layout, with the mining sequence being largely dictated by the quality of the blocks identified in the resource model. There will be no tailings or waste storage facility, with only oversize material from the screening plant being discarded by being placed back into the exhausted parts of the mine area.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has an estimated net present value, at a 5% discount rate, of A$33.2-million and an internal rate of return of 104.7%, with a payback of less 2.5 years.
Value
Capital expenditure (capex) is estimated at A$1.2-million, with a further moderate capital injection of A$600 000 in Year 6 to accommodate plant and throughput expansion.
Duration
Not stated.
Latest Developments
The scoping study has suggested that a full feasibility study be undertaken to ensure that the proposed establishment and production costs for the Pyramid Lake gypsum project are robust and can support a mining lease application.
This study should determine the capex and operating expenditure costs for the production of the Grade 2, Grade1 and Premium gypsum products (refinement of current model).
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Cohiba Minerals, tel +61 3 9692 7222, fax +61 3 9077 9233 or email admin@cohibaminerals.com.au.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation