Pilgangoora lithium/tantalum project – Stage 3, Australia
Name of the Project
Pilgangoora lithium/tantalum project – Stage 3.
Location
Pilbara, Western Australia.
Project Owner/s
Pilbara Minerals.
Project Description
A scoping study has demonstrated the Pilgangoora project’s significant scale; long-life, high-quality products; and expected low cost of operations, supporting its continued expansion pathway and Pilbara Minerals’ downstream participation strategy.
The Stage 3 study is based on the current reserves of 108-million tonnes. The project will increase the project’s processing capacity to 7.5-million tonnes a year to deliver average production of about 12-million tonnes a year of SC6.0 spodumene concentrate and about 1.1-million pounds a year of 30% tantalite concentrate over an estimated 15-year mine life.
The Stage 3 project will build from the current Stage 1 operation and the proposed Stage 2 project, through the construction of a parallel processing train. While the key process steps will remain unchanged, the build will involve the construction of an additional 2.5-million-tonne-a-year crushing circuit to complement the combined Stage 1 and 2 circuits processing five-million tonnes a year.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 10% discount rate of A$3.73-billion.
Capital Expenditure
The project is estimated at A$225.8-million. This is in addition to the previously announced Stage 2 capital expenditure of A$231-million.
Planned Start/End Date
It is currently estimated that construction of Stage 3 could start late in the second quarter if 2020, with commissioning starting early in the second quarter of 2021.
Latest Developments
The Stage 3 project final investment decision and delivery schedule will be determined by the progress of further feasibility studies, market demand analysis, customer requirements, the timing of any associated chemical conversion facility and project funding outcomes. A further consideration is the development timeline of any proposed chemical facilities that may be linked to Stage 3 offtake.
Key Contracts and Suppliers
Roskill Consulting Group (market analysis); Trepanier (geology and resources); DRA (process plant and infrastructure); ATC Williams (tailings management facility) and HydroConcept (water supply).
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Pilbara Minerals, tel +61 8 6266 6266 or email pilbaraminerals.com.au.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation