Paladin on track at Langer Heinrich

20th April 2023

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Work to restart production at the Langer Heinrich uranium mine, in Namibia, is on track and within budget, ASX-listed Paladin Resources said on Thursday.

In its quarterly report for the three months to March, the company noted that work at the project was some 40% complete at the end of the quarter, with first production still on track for the first quarter of the 2024 calendar year.

Some 600 personnel have been mobilised to site.

“Paladin continues to progress restart activities at the Langer Heinrich mine in Namibia. The work executed to date, combined with our well-defined pathway to production and on-site project execution team ensures that the project remains on time and budget with first production targeted for first quarter of 2024,” said Paladin CEO Ian Purdy.

“With a strong uranium contract book and a world-class asset in the Langer Heinrich mine, Paladin remains well positioned to deliver long-term value for our stakeholders.”

Restart costs for the Langer Heinrich operation have previously been estimated at $81-million, with the project’s life-of-mine production estimated at 77.4-million pounds over a 17-year mine life, at an estimated C1 cost of $27.40/lb.

Edited by Creamer Media Reporter

Comments

Showroom

SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 
Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024
Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.06 0.093s - 108pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: