New Mexico mine to cost less than $30m – Minera Alamos

4th October 2022

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

TSX-V-listed Minera Alamos has announced the results of a preliminary economic assessment (PEA) for its Cerro do Oro project, in Mexico, detailing plans for a 60 000 oz/y gold mine that will cost less than $30-million.

The project has an 8.2-year mine life, based on an initial mineable total of 59 000 t of mineralisation heap leached at an average rate of about 20 000 t/d.

The Cerro do Oro mine will require preproduction capital costs of $28.1-million and will be paid back in 11 months.

Minera Alamos purchased a used crushing plant, which reduces up-front capital requirements.

“Given the rampant inflationary pressures across the industry, it is a testament to Minera’s smart and nimble business model that a new mine could be developed at Cerro do Oro for the low capital intensity presented in the PEA,” commented president Doug Ramshaw.

The PEA, using metal prices of $ 1600/oz, delivered robust economics, with an aftertax net present value, using a 5% discount, of $150.5-million and an internal rate of return of 111%.

The project has a life-of-mine all-in sustaining cost of $873/oz.

“Leaning on our team’s collective experience in mine building in Mexico with capital and operating costs informed by the recent construction and ramp up of the Santana gold mine, the Cerro do Oro PEA is a game changer for Minera as we strive to reach our initial target of a 100 000-oz/y gold producer,” said Ramshaw.

Cerro do Oro’s updated inferred mineral resource estimate contains 67-million tonnes at 0.37 g/t gold, based on an upward revision of the base case resource metal price of $1 700/oz.

Edited by Creamer Media Reporter

Comments

Latest News

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
Updated 7 hours ago

Showroom

Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 
SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024
Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.058 0.091s - 107pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: