Moma titanium mine expansion, Mozambique
Name and Location
Moma titanium mine expansion, Mozambique.
Client
Kenmare Resources.
Project Description
The project involves increasing the Moma mine's production by about 50% to about 1.2-million tons a year of ilmenite and associated products.
Value
The costs associated with the Moma titanium minerals mine expansion have been revised to $350-million from an earlier estimate of $300-million.
Duration
Commissioning of the expansion project is expected by the end of 2012. Subsequent ramp-up in operations will enable full production from the expanded facilities during 2013 to take advantage of the prevailing robust market.
The feasibility study for the Phase 3 expansion is expected to be completed in 2012.
Latest Developments
Construction activities at Kenmare’s Moma titanium mine expansion project are nearing completion.
The company expects the contractor to hand over the wet concentrator plant B and the new dredge within the next few weeks, allowing Kenmare to initiate final commissioning and enabling the processing of first ore and the start of production ramp-up.
This follows the month-long staged plant commissioning activities undertaken by the various facilities’ operations team.
Key Contracts and Suppliers
E+PC (engineering, procurement and construction management contract).
On Budget and on Time?
The project was delayed into the second half of 2012. The costs associated with the expansion project have risen as a result of dimensional inaccuracies in structural steel sections delivered to site. The modifications to repair these inaccuracies and the additional resources brought to the site to enable completion by the end of this year have also impacted on costs.
Contact Details for Project Information
Kenmare Resources, tel +258 21 494921 or +258 21 499701, fax +258 21 499731 or email kenmaremaputo@intra.co.mz.
Brunswick South Africa, on behalf of the Aveng Group, tel +27 11 502 7300 or fax +27 11 268 5747.
E+PC, tel +27 10 205 1000 or fax +27 87 807 0143.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation