JOHANNESBURG (miningweekly.com) – Titanium minerals producer Kenmare Resources has extended the date for delivery of a budget to April 30.

The company on Tuesday said its project lenders and banking firm Absa have made “substantial progress” towards agreeing the prinicipal terms of a further financing amendement for the company’s projects in Southern Africa.

Kenmare operates the Moma mine, in Mozambique, which produces ilmenite, rutile and zircon.

The financing amendment remained subject to the finalisation of terms, approval by each lender and their insurers and approval by the Irish Takeover Panel.

Kenmare envisaged that the deal would extend the maturity of the current facilities and substantially reduce fixed amortisation requirements in favour of a cash-sweep mechanism.

In conjunction with the financing amendment, project lenders were considering the provision of a new super-senior debt facility, which would rank ahead of existing debt, and might be drawn to service working capital and other requirements as necessary.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 
Virtual Gas Network (Pty) Ltd
Virtual Gas Network (Pty) Ltd

Virtual Gas Network supplies compressed natural gas via a virtual gas distribution network.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.053 0.076s - 111pq - 2rq
Subscribe Now