Kenmare advises of lightning damage at its Moma mine

Kenmare Resources' Moma mine, in Mozambique

Kenmare Resources' Moma mine, in Mozambique

2nd March 2023

By: Marleny Arnoldi

Deputy Editor Online

     

Font size: - +

London-listed titanium and zircon producer Kenmare Resources has advised that power lines near its Moma mine, in northern Mozambique, were subject to an intense direct lightning strike, which cut out two of the powerline conductors and overwhelmed the mine’s lightning protection systems.

Kenmare says that, in addition to the damage to the power line infrastructure, many variable speed drives (VSDs) and electronic devices at the mine were also damaged, primarily at the three wet concentrator plants (WCPs).

The company explains that, in its 15 years of operating the Moma mine, this type of lightning damage has never occurred before.

Since the rainy season from November to April often brings widespread electrical storms to Mozambique, the company has a range of protection systems in place to minimise the impact on operations.

These systems include a rotary uninterruptible power supply system to ensure stable power to the mineral separation plant (MSP) and a synchronous condenser, which is a voltage stabilisation device that alleviates about 80% of the dips and spikes in power supply to the mine.

Kenmare states that mining operations were severely disrupted while repairs were carried out.

The company is working hard to recover lost production of heavy mineral concentrate, while ilmenite and rutile production is expected to be towards the lower end of production guidance for the year.

Owing to the company being able to draw down from intermediate stocks at the MSP, the guidance range for zircon and concentrates remains unchanged. 

Ilmenite production is set at between 1.05-million and 1.15-million tonnes, rutile at between 8 000 and 9 000 t and concentrates at between 37 000 and 41 000 t.

Kenmare advises that its shipping schedule has not been affected by the lightning damage or processing delays, since the MSP continued to operate and existing finished product inventories have been sufficient to allow for continued product shipments.

The WCP production capacity has since been restored at optimal operating levels and Kenmare is working to replace or repair the last of the damaged equipment, particularly the VSDs.

The company says it has insurance cover in place and is liaising with insurers to process claims related to the lightning strike.

Kenmare will announce in more detail the extent of the capital and operating cost impacts during its 2022 preliminary results presentation on March 22.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.119 0.154s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: