Kamoa-Kakula’s Phase 3 concentrator reaches commercial production

Kamoa-Kakula Copper Complex

Kamoa-Kakula Copper Complex

19th August 2024

By: Darren Parker

Creamer Media Senior Contributing Editor Online

     

Font size: - +

Dual-listed Ivanhoe Mines’ Phase 3 concentrator at the Kamoa-Kakula Copper Complex, in the Democratic Republic of Congo (DRC), has reached commercial production, the company announced on August 19.

Together, Kamoa-Kakula’s Phase 1, 2 and 3 concentrators achieved a combined monthly production record of 35 941 t of copper in July.

"Kamoa-Kakula's . . . production in July marks the onset of rapid copper growth over the second half of 2024, with Phase 3 on track to increase annualised production capacity from approximately 450 000 t to over 600 000 t,” Ivanhoe executive co-chairperson Robert Friedland said.

He noted that the company was also pursuing avenues to maximise copper production from Kamoa-Kakula's current operating footprint, with recoveries expected to increase through the company’s Project 95 programme, and overall throughput to also increase through the near-term debottlenecking of the Phase 3 concentrator.

He said Ivanhoe would now advance planning on Kamoa-Kakula's Phase 4 expansion, while exploration continued on the adjacent Western Foreland licences.

Kamoa-Kakula’s Phase 3 concentrator was completed ahead of schedule on May 28, with copper concentrate production starting on June 10.

The Phase 3 concentrator subsequently achieved commercial production. This accelerated ramp-up schedule was primarily owing to experience gained from the ramp-up of the Phase 1 and 2 concentrators that also achieved commercial production over a similar period.

The Phase 3 concentrator is consistently milling at the nameplate processing rate of five-million tonnes a year. The company said that milling had also exceeded nameplate capacity by as much as 19% over 24 hours on multiple occasions.

Commissioning of the fine-grinding mills is the final stage of ramp-up required to achieve steady-state production, increasing recovery from about 80% to the nameplate target of 86%.

The fine-grinding mills, manufactured by Finnish company Metso, are currently undergoing installation with commissioning expected to begin from the end of August.

Following the Project 95 basic engineering work that was recently completed on the Phase 1 and 2 concentrators, Kamoa Copper’s engineering team will soon begin study work targeting an increase in the Phase 3 concentrator’s recovery rate to more than 90%, as well as a further increase in processing capacity.

Since first production, the Phase 3 concentrator has produced more than 11 000 t of copper in concentrate. The first sale of copper concentrate produced by the Phase 3 concentrator took place in July, with all concentrate produced so far toll smelted at the nearby Lualaba copper smelter (LCS) in Kolwezi.

So far, more than 33 000 wet metric tonnes of copper concentrate have been delivered to LCS.

In the fourth quarter, prior to the heat-up of the onsite copper smelter at Kamoa-Kakula in early 2025, a portion of the Phase 3 copper concentrate will be stockpiled onsite, with the remainder delivered to LCS.

On a standalone basis, the Phase 3 concentrator is expected to produce about 150 000 t/y of copper. In addition to the Phase 1 and 2 concentrators, total copper production capacity at Kamoa-Kakula is expected to be more than 600 000 t/y, making it the third-largest copper mining operation globally.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Latest News

Osisko appoints Quin to board
Osisko appoints Quin to board
6th December 2024 By: Creamer Media Reporter

Showroom

Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 
John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 06 December 2024
Magazine round up | 06 December 2024
6th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.052 0.079s - 129pq - 2rq
Subscribe Now