Jubilee to deliver chromite concentrate in a fortnight
JOHANNESBURG (miningweekly.com) – Dual-listed mine-to-metals specialist Jubilee Platinum’s commissioning of chromite recovery and platinum group metals (PGMs) plants at its Hernic ferrochrome operation is progressing to schedule, with the first chromite concentrate product targeted within the next two weeks.
At full production, the project is expected to be the largest PGMs beneficiation plant of surface chrome tailings in South Africa, targeting the processing of 55 000 t/m of chrome and PGM-rich material.
The integration of the two circuits will start in February.
“We are excited with the progress as we complete the testing and commissioning of our Hernic project. The complexity of bringing such a large project into operation has been well managed through a disciplined commissioning programme and the support of our contracted engineering and project management partners,” said Jubilee CEO Leon Coetzer.
The commissioning of the PGM recovery plant would be the natural succession of the chromite recovery plant with integration of the two recovery plants targeted for February, he explained.
The commissioning activities include the structural, mechanical, electrical, control and instrumentation, piping and equipment testing; the pre-operational functional testing and operating of the equipment; and the integrated functional testing of process units in closed loop using process water to complete commissioning of mechanical and process control functionality of the integrated metallurgical process unit.
Lastly, Jubilee will undertake the final functional testing of the fully integrated metallurgical unit processes using process water prior to feeding through chromite and PGM material.
“The final step of integrating the chromite recovery plant into Hernic’s current operations to receive Hernic feed material and ramping up of production, is targeted for completion within the next two weeks,” Coetzer said.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation