https://www.miningweekly.com

Ivanhoe aiming to develop DRC copper mine bigger than Grasberg and Oyu Tolgoi

12th April 2019

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Canada-headquartered Ivanhoe Mines is considering an expanded copper mining development in the Democratic Republic of Congo (DRC), which will position the Kamoa-Kakula mine as the world’s second-largest after the giant Escondida mine of BHP and Rio Tinto, in Chile.

At an expanded production rate of 18-million tonnes a year, with peak copper output of 740 000 t/y, Kamoa-Kakula will produce more than the projected 2025 output of Grasberg, in Indonesia, and Oyu Tolgoi, in Mongolia.

The expanded plan for Komoa-Kakula is based on an initial six-million-tonne-a-year mine at Kakula, followed by two six-million-tonne-a-year mines at Kansoko and Kakula West, and a direct-to-blister smelter. The development scenario will require an initial $1.1-billion for Kakula, with the subsequent mines and smelter to be funded by cash flows from the first mine.

Ivanhoe, which owns 39.6% of the project with Zijin Mining (39.6%), Crystal River Global (0.8%) and the DRC government (20%), has started underground development at the planned initial Kakula mine and reported last week that the project was making “excellent progress”.

Construction of the twin northern declines has been completed, with ongoing underground development activities now focused on constructing lateral access drives and ventilation raises. Development of a ventilation decline on the southern side of the Kakula orebody is under way.

Design for the main Kakula decline conveyor system and initial two truck tips at the bottom of the decline is well advanced. Most of the major procurement packages have been ordered and construction will get under way shortly, with completion scheduled for the end of this year.

Further, Ivanhoe reported that discussions for financing the construction of the initial six-million-tonne Kakula mine were progressing and that Citic Metal – its largest shareholder – was assisting with the negotiations. The company is talking to international and China-based financial institutions.

Initial production from the Stage 1 development is scheduled for early 2021. Stage 1 production is projected to have a copper grade of 6.4% over the initial ten years of operations, resulting in an estimated production of 291 000 t.

The Komoa-Kakula project has a total mineral resource of 1.39-billion tonnes, grading 2.64% copper and containing 80.6-billion pounds of copper at a 1% copper cutoff grade, with a minimum thickness of 3 m.

Meanwhile, Ivanhoe reported that it had spent more than C$800-million to advance its three mine projects in Southern Africa in 2018. Besides Kamoa-Kakula, these include the Kipushi project, in the DRC, and the Platreef project, in South Africa.

For 2019, the company’s main objectives at Platreef will be the continuation of Shaft 1 construction and the completion of early works construction of Shaft 2. At Kipushi, the principal objectives are the completion of the feasibility study and the continued upgrading of mining infrastructure.

The company has budgeted to spend $90- million on further development at the Platreef project, $57-million at Kipushi, $16-million on regional exploration in the DRC and $30-million on corporate overheads for 2019 – as well as its proportionate funding of the Kamoa-Kakula project, expected to be $101-million for 2019.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 
John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.13 0.169s - 88pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: