Honeymoon uranium restart project, Australia

Map of Honeymoon uranium project site

13th August 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Honeymoon uranium restart project.

Location
South Australia.

Project Owner/s
ASX-listed Boss Energy.

Project Description
An enhanced feasibility study on the project has resulted in a 22.5% increase in production capacity, compared with a 2020 feasibility study on the project.

The project comprises two main exploration areas – the Eastern and Western tenement regions – with one granted Mining Lease 6109, totalling a 2 595 km2 tenement package.

The enhanced feasibility study was based on revised capital and operating estimates, a revised wellfield design plan and revised economic assumptions reflecting continued improvement in the outlook

The study is based on using only 36-million pounds of the project’s global Joint Ore Reserves Committee-compliant resource of 71.6-million pounds.

The study proposes the removal of the existing solvent-extraction (SX) plant and replacing it with ion-exchange (IX) capacity. IX will be used as the only uranium-recovery technology in two stages to match the wellfield development schedule.

The startup phase will produce 1.63-million pounds of uranium in Year 2. Works for this phase include replacing the existing SX processing facility with three NIMCIX trains.

Additionally, various modifications will be made to improve performance in the leach liquor, precipitation, drying and packaging circuits to allow for the production of uranium by replacing the existing vacuum dryers with a calciner kiln.

The ramp-up IX circuit will mirror the startup NIMCIX circuit.

In the ramp-up phase, production will increase to 2.45-million pounds a year in Year 3, with the installation of a duplicate IX facility that will operate in parallel with the startup IX facility.

Life-of-mine production has increased from 20.74-million pounds in the 2020 feasibility study to 21.81-million pounds in the enhanced feasibility study.

The project’s mine life has decreased from 12 to 11 years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The enhanced feasibility study estimates a pretax net present value, at an 8% discount rate, of $308.75-million, an increase of 35%, compared with the 2020 feasibility study.

The forecast internal rate of return is estimated at 47.1%, compared with 51.4% in the 2020 feasibility study.

Payback has decreased from four years in the 2020 feasibility study to 3.5 years in the enhanced feasibility study.

Capital Expenditure
The cost of the project has increased from $69.98-million to $80.01-million.

Planned Start/End Date
Not stated.

Latest Developments
Boss is focusing on progressing offtake negotiations and project financing efforts while advancing the project towards development.

The company is also developing a plan to increase the production profile and extending mine life through the development of satellite resources, and maintaining a strong exploration focus and programme on near-mine and regional targets.

Key Contracts, Suppliers and Consultants
GR Engineering Services (process plant redesign); AMC Consultants (mineral resources estimate); Australian Nuclear Science and Technology Organisation Minerals Laboratories (supporting testwork for the optimised NIMCIX and elution design); Groundwater Science (wellfield design and production scheduling); Inception Group (in situ recovery support); and Infinity Corporate Finance (financial modelling services).

Contact Details for Project Information
Boss Energy, tel +61 61 8 9388 1474 or email info@readcorporate.com.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Aqs image
AQS Liquid Transfer

AxFlow AQS Liquid Transfer (Pty) Ltd is an Importer and Distributor of Pumps in Southern Africa

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (10/05/2024)
10th May 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.151 0.206s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: