https://www.miningweekly.com
Africa|Construction|Contractor|Design|Gas|Gold|Mining|Power|PROJECT|Resources|Road|Equipment|Maintenance|Infrastructure|Bearing|Operations
Africa|Construction|Contractor|Design|Gas|Gold|Mining|Power|PROJECT|Resources|Road|Equipment|Maintenance|Infrastructure|Bearing|Operations
africa|construction|contractor|design|gas|gold|mining|power|project|resources|road|equipment|maintenance|infrastructure|bearing|operations

Gruyere gold project, Australia – update

2nd October 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Gruyere gold project.

Location
The project is located in the Yamarna greenstone belt, about 200 m east of Laverton, in Western Australia.

Project Owner/s
The project is a joint venture (JV) between Australia’s Gold Road Resources and South Africa’s Gold Fields.

Gold Road and Gold Fields entered into a 50:50 JV over the Gruyere project in November 2016. The South Africa-based major paid A$350-million for its share in the project.

Project Description
A feasibility study has confirmed Gruyere as one of the longest-life, lowest-cost undeveloped gold deposits in the world, with an estimated mine life of 12 years. The expected ounces of gold recovered over the life of the project are estimated at 3.47-million ounces.

The project has total proven and probable reserves of 91.6-million tonnes grading 1.2 g/t gold. The Gruyere JV has also awarded mining leases over additional mineral resources at Central Bore and Attila-Alaric, which do not form part of the Gruyere project feasibility study.

Development of the project is based on a large openpit mine, conventional semiautogenous grinding/ball mill circuit and gravity/carbon-in-leach (CIL) plant, with throughput of 7.5-million tonnes of fresh ore a year and up to 8.2-million tonnes of oxide ore a year.

A mining contractor will undertake activities, with Gold Road providing technical and managerial direction.

The feasibility study proposes that the pit be mined in four stages. Stages 1 and 2 comprise two independent pits at the northern and southern ends of the deposit. Stage 3 will combine the two starter pits and Stage 4 will cut back to the final pit design.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value (NPV), at an 8% discount rate, of A$486-million and an internal rate of return (IRR) of 24% at a A$1 500/oz gold price. At a A$1 750/oz gold price, the NPV increases to A$910-million, with an IRR of 35%.

Capital Expenditure
In July 2018, an independent third-party review of the definitive estimate for the Gruyere gold project increased the capital cost estimate from A$532-million to A$621-million.

The updated capital cost included scope changes and force majeure costs of A$30-million, as well as a A$30-million contingency.

Key contributors to the increased capital cost included a range of scope changes that will improve the operability and maintainability of the process plant and infrastructure, as well as advance operating and capital expenditure, including the buying of additional equipment previously intended to be hired.

Costs will be funded from existing cash and working capital facilities.

Planned Start/End Date
Gruyere poured its first gold at the start of July 2019; the project is now ramping up to nameplate capacity.

Latest Developments
A ball mill motor bearing failure occurred on a restart of the Gruyere processing facility in September, after a scheduled maintenance shutdown. Upon detection of the failure, a specialist team was mobilised to site.

Following a thorough inspection, the root cause of the failure has been determined, rectification measures have been taken and the available spare has been installed, with normal processing operations having resumed.

As a result of the ball mill motor bearing failure and additional plant downtime early in the quarter, Gold Road expects gold produced for the September quarter to be between 53 000 oz and 57 000 oz.

Full-year production guidance for 2020 is expected at 250 000 to 270 000 oz, down from the previous estimate of between 250 000 to 285 000 oz. 

Key Contracts,  Suppliers and Consultants
Amec Foster Wheeler and Civmec (EPC), APA Group (pipeline and gas-fired power station), MACA (airstrip) and MACA and ACJV (Yeo borefield construction), Amec Foster Wheeler Civmec JV (EPC contractor).

Contact Details for Project Information
Gold Road Resources, tel +61 8 9200 1600, fax +61 8 9481 6405 or email perth@goldroad.com.au.

Edited by Creamer Media Reporter

Comments

Showroom

Alco-Safe
Alco-Safe

An unmanned breathalyser that is made to be tough and simple to use. Can be used in any environment for operator-free breathalyser testing.

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hyphen, Eva mine, ferrochrome price make headlines
Hyphen, Eva mine, ferrochrome price make headlines
27th March 2024
Resources Watch
Resources Watch
27th March 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.129 0.18s - 94pq - 2rq
Subscribe Now