Grootegeluk Medupi expansion project, South Africa
Name and Location
Grootegeluk Medupi expansion project (GMEP), Limpopo, South Africa.
Client
Exxaro Resources.
Project Description
The project entails a brownfield expansion of Exxaro's Grootegeluk mine. Coal will be mined from the existing opencast pit at an accelerated rate, with the mine's current production increasing from 19-million sales tons a year to 34-million sales tons a year.
The brownfield expansion requires new developments in mining processes, screening, beneficiation and the stockyard. The project will use new technology to enable the delivery of high-quality product. These will include semimobile crushers and tippers, dry screening of the material smaller than 6 mm, large-coal dense-medium separator (DMS) (larcodem) units and large cyclones.
The expansion will be mined with semimobile in-pit tip-and-crusher units supplied by the truck and loading operations. The tipping bins and crushers will be used as mobile units in the pit and will move as the mine moves forward.
The coal beneficiation process will be handled through two new DMS facilities, the Grootegeluk 7 and Grootegeluk 8 beneficiation plants, which will be constructed at the mine.
The run-of-mine (RoM) coal will be screened through the coarse-coal screens to remove material smaller than 40 mm. Material smaller than 6 mm will be screened out dry for direct mixing into the final product, which eliminates the need for slimes dams.
Material bigger than 40 mm and smaller than 100 mm will be beneficiated in the larcodems, while material smaller than 40 mm will be beneficiated in the large cyclones.
The fines in the process water will be recovered in the thickener dams and dried in the filter presses to be mixed into the final product. When water gets into contact with the coal, it will not be allowed into the environment. Polluted water will be kept in the loop circulation process for reuse.
The stockyard will accommodate about 430 000 t of coal, which will be stacked with two stackers and reclaimed with one reclaimer. The RoM stockpiles will be introduced between the mine, the plant and the discard stackers to support continuous production.
About 740 housing units are also being built to cater for the project team and the expanded workforce.
The expansion is part of the 40-year coal supply agreement, at an average of 14.6-million tons a year, that Exxaro secured with Eskom to supply the utility's new Medupi power station, which is under construction near Lephalale, in Limpopo.
Value
It is expected that the total project expenditure will be about R10.2-billion. The revised budget has increased by R700-million, owing to a combination of factors, including additional escalations, labour unrest, steel shortages and additional scope that has been added to the project.
GMEP expenditure to date is R7.1-billion.
Duration
The coal supply ramp-up will commence during the first half of 2013 and is expected to continue until the second half of 2016.
Latest Developments
The GMEP is 92% complete.
The project will be implemented in three phases to allow for the delayed ramp-up of Eskom to tonnages. Phase 1 includes the first mining equipment, the run-of-mine bunker, the total plant complex and the total dispatch facilities. It is expected that coal will be produced through the plant during the first half of 2013.
Phase 2, which is 75% complete, includes the conveyors and semimobile tip-and-crusher units in the pit. It is forecast to be completed by the third quarter of 2013.
Phase 3 includes the remaining mining equipment and the housing project of 740 units, forecast to be completed in the first half of 2013.
The backfill project at Grootegeluk is progressing well with Phase 1 forecast to be completed in the third quarter of 2013 and Phase 2 by the end of 2014.
Key Contracts and Suppliers
Packages awarded:
LSL Consulting, SSG Consulting and Engineering & Projects Company (E+PC) (design); Arup (civils); Melco (conveyor equipment supplier) Consolidated Power Projects (overhead power lines and transformers); M Projects (building upfront infrastructure); Concor Holdings (bulk earthworks plant area, blending and load out); PRG Electrical Engineering & Services (construction power); MMD Mineral Sizing (Africa) (inpit crushing system); Basil Read (in-plant workshop); Makeshift (relocation of piping and civil services); FLSmidth (stackers and reclaimers); Stefanutti Stocks Civils (RoM area civil), Aveng Engineering & Projects Company (coal-washing plant), Wade Walker (electrical and instrumentation work), SMEI Projects (assisting SCMEIPP − plant area civil, thickeners civil, plant area structural, mechanical, platework and piping [SMPP], mining area bulk earthworks, buildings administration, blending and load out civil, 11 kV distribution, low-voltage and instrumentation plant area, blending and load out SMPP, filter plant SMPP and RoM area SMPP) and Amrec (planning and scheduling).
On Budget and on Time?
The construction of the GMEP continues to progress as planned and within budget.
Contact Details for Project Information
Arup, Joe Strydom, tel +27 11 218 7600 or email johannesburg@arup.com.
Basil Read, tel +27 11 418 6300 or fax +27 11 418 6333; or investor relations, Enna Kruger, tel +27 11 418 6375, fax +27 11 418 6334 or email ekruger@basilread.co.za.
Conco, tel +27 11 805 4281, fax +27 11 805 1132 or email conco@conco.co.za; or investor relations, Raoul Gamsu, tel +27 11 722 7441 or Ivor Klitzner, tel +27 11 722 7428.
Concor Mining, tel +27 11 495 2222, fax +27 11 495 2488 or email info.mining@concor.co.za.
E+PC, Elzaan Koegelenberg, tel +27 10 205 1000, fax +27 87 807 0143 or email elzaan.koegelenberg@e-pc.co.za.
Exxaro Resources corporate communication manager Hilton Atkinson, tel +27 12 307 4843 or email hilton.atkinson@exxaro.com; or GM of GMEP Joe Meyer , email joe.meyer@exxaro.com.
FLSmidth head of investor relations and corporate communications Pernille Andersen, tel +45 36 18 1887, fax +45 36 16 1922 or email pefa@flsmidth.com.
LSL Consulting, tel +27 11 789 8138.
M Projects, tel +27 31 902 9755, fax +27 31 902 2903 or email mprojects@cybertrade.co.za.
MMD Mineral Sizing (Africa), tel +27 11 608 4801, fax +27 11 608 4848 or email sizers@mmdafrica.co.za.
PRG Electrical Engineering & Services, tel +27 16 889 3109.
SMEI Projects, tel +27 11 914 4101, fax +27 11 914 4108 or email smei@smei.co.za.
SSG Consulting CEO Steven Golding, tel +27 12 345 6779, fax +27 86 697 1924 or email steven.golding@ssgconsulting.co.za.
Stefanutti Stocks Civils, tel +27 11 571 4300, fax +27 11 393 2366 or email civils@stefstocks.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation