Eskom aims to unlock 500 MW of renewables from second land-lease tender

Eskom power lines

Photo by Creamer Media

26th January 2023

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

Eskom will host site visits on February 7 for independent power producers (IPPs) interested in four new parcels of grid-ready land in Mpumalanga that the utility will make available under its long-term lease programme for the development of up to 500 MW of renewable-energy generation.

The request for proposals (RFP), which was published in December, marks the launch of the second phase of the Land Lease Programme launched in April last year and focuses on land parcels within the borders of the Lekwa and Victor Khanye local municipalities.

During the first phase, 17 land parcels around the Majuba and Tutuka power stations, also in Mpumalanga, were made available.

In October, Eskom concluded 25- to 30-year lease agreements for land covering a total of 6 184 ha with five IPPs, namely HDF Energy South Africa, Red Rocket, Sola Group and Mainstream Renewable Power Developments South Africa.

It is estimated that those initial parcels could accommodate renewables projects with a combined capacity of 1 800 MW and a recently released National Energy Crisis Committee roadmap indicated that the land-lease programme could help add 2 142 MW after 2024.

Eskom said the new land parcels being released were also in close proximity to network connection points, which would reduce the time required to build new grid connection infrastructure.

Access to the grid has emerged as a key constraint to renewables development, particularly in the Cape provinces and Eskom is, thus, hoping to attract investors to areas where its network is less limited, but where the solar and wind resources are less potent.

The utility also reiterated that it would not be the buyer of the electricity arising from the sites, but would facilitate a process to enable the IPPs to wheel the power over the Eskom grid, either for their own consumption, or to sell on to other consumers.

The closing date for the RFP is 10:00 on February 27.

Edited by Creamer Media Reporter

Comments

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.138 0.18s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: