Electricity disruptions threaten manufacturing output, Seifsa warns

23rd January 2015

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

  

Font size: - +

South Africa is on its way to shedding 23% of production in the metals and engineering sector should the nation’s electricity woes not be resolved.

The Steel and Engineering Industries Federation of Southern Africa (Seifsa) has reiterated its warning on the impact of load- shedding and electricity disruptions on the sector after Statistics South Africa released the lower-than-expected manufacturing production and sales findings for November.

“The warnings from [State-owned power utility] Eskom regarding the possibility of such occurrences during the year are of huge concern,” Seifsa chief economist Henk Langenhoven said.

Eskom this week warned that the national grid would remain “extremely constrained” as “even more” businesses reopen, workers return to work and scholars head back to school after the December holidays.

“The system remains vulnerable, meaning that any extra load or faults in the system may necessitate the need to implement load-shedding,” the parastatal said in a weekly update.

“The impact of electricity supply disruptions to the metals and engineering sector was clearly visible in the 1% seasonally adjusted decline in manufacturing production numbers, when November 2014 is compared with October 2014,” Langenhoven commented.

The potential impact of electricity disruptions on the sector had kept other industry commentators cautious on the outlook for manufacturing for 2015.

BNP Paribas Cadiz economist Jeffrey Schultz noted the Purchasing Managers Index manufacturing statistics, due to be released later this week, would likely reflect the concerns over electricity supply problems.

The Nedbank Economic Unit commented in a flash comment to clients that the outlook for 2015 remained subdued, given the ongoing power outages. This was in addition to the threat of renewed labour disruptions, expectations of slower growth in key export markets and sharply lower international commodity prices.

Langenhoven said that, while actual November production numbers were “better than expected”, should the outages continue further into 2015, the predicted double-digit loss of production might prove “ominously close to reality”.

While production growth of more than 2% was “hoped for” during 2014, he said, the cumulative effect of the production disruptions during 2014 had the opposite result, leading to a 2.5% contraction.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sulzer Pumps (SA) (Pty) Ltd
Sulzer Pumps (SA) (Pty) Ltd

Sulzer South Africa, established in 1922, partners with critical industries like power, oil & gas, water, mining, and chemicals to boost...

VISIT SHOWROOM 
Aluminium Federation of South Africa
Aluminium Federation of South Africa

The Aluminium Federation of South Africa (AFSA), is the voice of the South African aluminium industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.055 0.77s - 110pq - 2rq
Subscribe Now