Denison inches closer to building Canada’s next new uranium mine
Toronto-listed Denison Mines has submitted the final environmental impact statement (EIS) for the Wheeler River uranium project with the Canadian Nuclear Safety Commission (CNSC).
The submission follows the completion of the technical review phase of the federal environmental assessment (EA) approval process.
Denison president and CEO David Cates noted that this development brings the company one step closer to building Canada's next new uranium mine, which would also be the country’s first in-situ recovery (ISR) uranium mining project.
“Owing, in large part, to the use of the ISR mining method, the EIS evidences that the project can be constructed, operated, and decommissioned while achieving a superior standard of environmental sustainability when compared to conventional uranium mining operations,” says Cates.
With the final EIS now filed, the CNSC staff will review the submission for acceptance and prepare recommendations for the commission members who will sit on the panel for the project's public hearing. The hearing will provide Denison with an opportunity to demonstrate the project's alignment with both regulatory requirements and community expectations. While the exact date for the hearing has not yet been set by the CNSC, it is expected to be determined once the final EIS submission has been accepted.
In parallel with the federal EIS submission, Denison has also made progress in obtaining the necessary licences for the project. The company was recently informed that it had successfully met the requirements for a CNSC licence to prepare and construct a uranium mine and mill. This allows the CNSC to potentially make a licensing decision at the same time as the EA approval.
Last month, Denison also submitted a final EIS to the Saskatchewan Ministry of Environment (MoE), largely mirroring the document submitted to the CNSC. Although the technical review comment period was completed by the MoE in late 2023, Denison chose to delay finalising the provincial EA approval in order to incorporate the majority of modifications recommended during the federal technical review process.
This approach aims to streamline the provincial EA process, with the company expecting a single Ministerial decision following a public review period. This provincial review began in November 2024 and is expected to conclude in December.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation