PERTH (miningweekly.com) – Copper miner Sandfire Resources has reported an increase in copper production from its DeGrussa operation, in Western Australia, as the ramp-up of the underground mine continued.

The miner said on Thursday that the underground operation had achieved a run rate of 1.4-million tonnes a year during the month of September, just shy of its 1.5-million-tonnes-a-year capacity. The plant nameplate was maintained during the quarter, with copper recovery increasing with the removal of openpit ore from the blend.

During the September quarter, the DeGrussa mine delivered 16 446 t of copper concentrate, compared with the 14 293 t delivered in the previous quarter, and 8 613 oz of gold, compared with the 11 284 oz delivered in the three months to June.

Sandfire said that concentrate and metal production would be weighted towards the second half of the financial year, owing to the expected variability in mined head grade across different stopes, as part of the underground mine plan between the December quarter of 2013 and the March and June quarters of next year.

For the full year, Sandfire’s production target remained unchanged at between 65 000 t and 75 000 t of contained copper, and between 35 000 oz and 45 000 oz of gold.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Hanna Instruments (Pty) Ltd
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
Iritron
Iritron

Iritron delivers advanced automation, control, and optimisation solutions to the Mining, Minerals & Metals, Consumer Package Goods and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.05 1.14s - 134pq - 2rq
Subscribe Now