https://www.miningweekly.com
Crushing|Engineering|Exploration|flotation|Platinum|PROJECT|Resources|Trucks|Products|Operations
Crushing|Engineering|Exploration|flotation|Platinum|PROJECT|Resources|Trucks|Products|Operations
crushing|engineering|exploration|flotation|platinum|project|resources|trucks|products|operations

Crawford nickel sulphide project, Canada – update

Image of Canada flag and processed nickel

15th July 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Crawford nickel sulphide project.

Location
Timmins, in Ontario, Canada.

Project Owner/s
Canada Nickel Company.

Project Description
A preliminary economic assessment (PEA) on the Crawford project has confirmed its robust economics.

The PEA has demonstrated the potential to develop a phased conventional nickel sulphide concentrator producing nickel and magnetite concentrates.

Crawford will be a conventional openpit mine/mill operation, powered by zero-carbon electricity while using trolley trucks and electric rope shovels to minimise its carbon footprint through reduced diesel consumption.

Average production is estimated at 34 000 t/y nickel, with production peaking at 42 000 t/y. Production will include significant iron and chrome by-products of 860 000 t/y and 59 000 t/y respectively.

The process plant will use a conventional milling operation comprising rushing, grinding, desliming and flotation operations consistent with other ultramafic nickel operations. The process plant will be constructed in three phases.

Phase 1 will have a steady-state throughput of 42 500 t/d using a single 36 ft x 24 ft semiautonomous grinding mill and a 26.5 ft × 44 ft ball mill grinding circuit. Phase 2 will double throughput, starting in Year 4, by mirroring the first line. Phase 3 will raise production to the ultimate rate of 120 000 t/d through the addition of secondary crushing, a third ball mill and additional downstream capacity.

About 842 000 t of nickel, 21-million tonnes of iron and 1.5-million tonnes of chrome is expected to be produced over the project’s 25-year mine life.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an estimated after-tax net present value, at an 8% discount rate, of $1.2-billion and an internal rate of return of 16%.

Capital Expenditure
Phase 1 will cost about $1.19-billion, Phase 2 about $534-million and Phase 3 is estimated at $194-million.

Planned Start/End Date
Not stated.

Latest Developments
Canada Nickel has more than doubled the measured and indicated mineral resources of its Crawford project to 1.43-billion tonnes grading 0.24% nickel.

The updated mineral resource estimate for the project, which was published on July 6, was largely driven by outstanding exploration success in the East Zone area of the project.

The inferred resource is at 670-milllion tonnes grading 0.23% nickel.

The measured and indicated resources also include 93-million tonnes of iron, 8.5-million tonnes of chromium, 183 000 t of cobalt and about one-million ounces of palladium and platinum.

Canada Nickel expects the final feasibility study resource to support the upper end of its mine plan target of producing 1.3- to 1.8-billion tonnes.

The Crawford feasibility study is said to be on track for completion by the end of the year and will incorporate resources for the project’s North Zone and Western Extension, totalling 53 holes combined.

Key Contracts, Suppliers and Consultants
Ausenco Engineering Canada (PEA).

Contact Details for Project Information
Canada Nickel Company, email info@canadanickel.com.

Edited by Creamer Media Reporter

Comments

Showroom

Sandvik Mining and Rock Solutions
Sandvik Mining and Rock Solutions

We engineer an extensive range of underground drill rigs for mining development and production. Available in a variety of feed lengths, boom...

VISIT SHOWROOM 
TGOOD
TGOOD

At TGOOD, we pride ourselves on our passionate team of professionals. As a world leader in pre-fabricated outdoor electric substation buildings, we...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (01/12/2023)
1st December 2023
Photo of Martin Creamer
Jupiter Mines, Copper 360 and DRDGold make headlines
1st December 2023
Magazine round up | 01 December 2023
Magazine round up | 01 December 2023
1st December 2023

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.185 0.234s - 93pq - 2rq
Subscribe Now