Costs rise at Ewoyaa as DFS is delivered

29th June 2023

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – A definitive feasibility study (DFS) into the Ewoyaa lithium project, in Ghana, has increased the project’s cost estimate from the $125-million estimated in the prefeasibility study (PFS) to $185-million.

Triple-listed Atlantic Lithium on Thursday reported that the DFS was based on a 3.6-million-tonne spodumene concentrate production over a mine life of 12 years. The DFS estimated a post-tax net present value of $1.5-billion with a free cash flow of $2.4-billion and life-of-mine revenues of $6.6-billion.

The study also estimated C1 cash operating costs of $377/t of concentrate free-on-board, after by-product credits from conventional opencut mining, and an all-in sustaining cost of $610/t.

“The DFS has reaffirmed the Ewoyaa lithium project’s impressive economic outcomes and profitability potential, providing improved confidence in Ewoyaa’s ability to become a significant, near-term producer of spodumene concentrate,” said Atlantic CEO Keith Muller.

“The study indicates payback within only 19 months and maintains a low capital intensity, further reinforcing Ewoyaa’s position among the leading pre-production hard rock lithium assets globally.

“The increase in capex from the PFS results from the inclusion of the modular dense media separation (DMS) units and the increased throughput of 2.7-million tonnes a year. Early revenue generated by the modular DMS units will reduce peak funding requirement for the mine build, strongly justifying these developments. Furthermore, this will provide a valuable opportunity to train national staff and engineer out any mining, materials handling or logistics bottlenecks ahead of large-scale operations commencing for a potentially quicker commissioning phase,” said Muller.

“The deployment of the modular DMS units has been reallocated from Stage 2 to Stage 1 of the project’s development. Stage 2 includes the evaluation of a Feldspar circuit, a by-product of the DMS process that we intend to supply to the local Ghanaian ceramics market, and a flotation circuit, further enhancing the project’s economics.

“Ewoyaa’s favourable mineralogy enables a simple flowsheet comprising a three-stage crushing facility and DMS processing from conventional, openpit mining to produce a spodumene concentrate proven suitable for carbonate, sulphide or hydroxide conversion. Due to its grade, the project’s coastal location and against the backdrop of the global decarbonisation movement, demand from off-takers for product from Ewoyaa has been strong.”

Atlantic has previously said that the company was hoping to be in production at Ewoyaa within the next two years.

Lithium major Piedmont is working towards a 50% stake in Ewoyaa, spending $17-million on exploration funding and the completion of a DFS, and also committing to half of the capital cost to develop the project.

 

Edited by Creamer Media Reporter

Comments

Latest News

Showroom

Actom image
Actom

Your one-stop global energy-solution partner

VISIT SHOWROOM 
Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.125 0.159s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: