Cobre achieves positive cashflow from newly owned Sierra Atacama project
ASX-listed copper producer Cobre has achieved positive operating cashflow at the Sierra Atacama project, in Chile, within two months of assuming control of the operation.
The company reported a cashflow of $644 000, or A$900 000, in April, and $601 000, or A$860 000, in May.
Cobre expects to remain profitable through June and beyond with performance continuing to strengthen as the year progresses.
Since assuming operational control of the project at the end of March, Cobre has been executing a structured turnaround programme across the existing underground mine and processing operation, including to address the fundamental drivers of cathode output, product quality and unit cost.
Cobre says the results have been immediate and measurable, with improvements having been achieved across mined head grade, leach recovery, cathode quality, production stability and operating costs.
"The Sierra Atacama turnaround programme underpins our broader six-part value-rerate programme for the project," says Cobre CEO Adam Wooldridge. He adds that two consecutive months of positive operating cash flow from the project mark a meaningful financial turning point for Sierra Atacama.
While the copper price has been supportive, Cobre notes the continuing impact of geopolitical tensions in key cost inputs, including sulphuric acid and diesel.
Cobre says it is working closely with key suppliers to manage these costs and improve operating resilience.
Meanwhile, Cobre is implementing a structured ramp-up to 700 t a month of copper cathode with strategic investments being made into the mine fleet, ventilation, fortification, and plant and crusher maintenance.
Wooldridge confirms the company's focus in the coming months will be on increasing underground development to ensure sustained access to higher-grade material and support a more consistent production profile.
Cobre aims to achieve a 96% increase in quarterly copper cathode output over four quarters this year. The January to March quarter had 764 t of copper cathode output, which grew to 879 t in the April to June quarter, with further increases to 1 200 t and 1 500 t, respectively, planned for the next two quarters.
The company targets 400 t a month of copper cathode output in its stabilisation phase, before ramping up to between 500 and 700 t a month over the next 12 months.
Should Cobre introduce openpit mining successfully, production can be expanded to the plant's nameplate capacity of 20 000 t/y of copper cathode, producing 1 500 t a month, which will generate between $8-million and $10-million, or A$10-million and $14-million, a month in operating cashflows.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation