https://www.miningweekly.com
Aggregate|Coal|Construction|Contractor|PROJECT|Projects|System
Aggregate|Coal|Construction|Contractor|PROJECT|Projects|System
aggregate|coal|construction|contractor|project|projects|system

CIL coal washery project delays attract Coal Ministry flak

25th February 2019

By: Ajoy K Das

Creamer Media Correspondent

     

Font size: - +

KOLKATA (miningweekly.com) – State-run Coal India Limited’s (CIL’s) ambitious plans of ramping up coal washing capacity has been hit by time overruns.

The delays in operationalising various coal washery projects has attracted criticism from the Coal Ministry at a recently held review meeting, during which the Coal Secretary noted that timely completion of the projects was “critical”. The Secretary noted that the government was concerned over delays and that the coal miner should implement software that would enable comprehensive micro-level monitoring of each project under implementation by its subsidiaries.

The projects reviewed include Dahibari, Patherdih-I, Madhuband, Patherdih II, Bhojudih, Dugda and Moonidih washeries being implemented by CIL subsidiary, Bharat Coking Coal Limited (BCCL).

Other projects facing delays are Tapin, Kathara, Ashok, Karo and Konar washeries being implemented by CIL subsidiary Central Coalfields and Ib Valley, Basundhar, Hingula and Jagannath washeries of Mahanadi Coalfields and Kusmunda and Baroud washeries of South Eastern Coalfield, a review of the minutes of the meeting revealed.

CIL has undertaken setting up 18 coal washeries across the country with an aggregate capacity of 95.6-million tons a year.  Currently, the miner operated 15 coal washeries at its pitheads, including 11 for coking coal, with total capacity of 36.8-million tons a year.

Representatives of various CIL subsidiaries present at the meeting cited a range of reasons for time-overrun suffered by the projects. For example, BCCL cited that Dahibari project could not be made operational owing to law and order problems at the plant location.

As for delay at the Patherdih I project, BCCL cited that a contractor had not been able to complete the track hopper system for receiving coal as per specifications laid down by Indian Railways and that the miner would need to allot the work to another contractor leading to delays.

In case of Patherdih II project, the miner informed that Ministry that while land had been handed over for construction of the washery, work could not started owing to encroachers on the land and that the local government would need to free the land of such encroachers to enable the project to be completed by revised deadline of 2020.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

Latest News

Anglo American's corporate head office in South Africa
Anglo shareholder LGIM says BHP approach 'unattractive'
Updated 7 hours ago By: Reuters
The combined entity will have a leading portfolio of tier-one assets, focused on iron-ore, metallurgical coal and future facing commodities, including potash and copper.
BHP makes £31bn offer for Anglo American
25th April 2024 By: Mariaan Webb

Showroom

Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 
Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.181 0.215s - 89pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: