The Blackwater mine, currently under construction in central British Columbia, remains on track for its first gold pour in the second half of next year, despite the temporary slowdown as a result of wildfire activity last month.
Project developer Artemis Gold in July temporarily reduced the number of nonessential staff and contractors because of an uncontrolled wildfire reaching the immediate vicinity of the mine site.
The damage to property was minimal and construction activities resumed in early August, with more than 400 people back on site.
Artemis says that while it is not making any changes to its initial capital expenditure (capex) guidance for the project, it is assessing the impact of the wildfire on its estimates.
Any cost impact depends on factors such as contractual remedies and insurance recoveries available to the company and its contractors.
The initial capital to complete to first gold pour is estimated to range between C$730-million and C$750-million, of which the company had incurred about C$186-million by the end of June.
Artemis chairperson Steven Dean comments that the project remains fully funded and is about 27% complete.
He notes that the company has formed strong partnerships with local communities and First Nations.
Blackwater will be one of the biggest gold mines in British Columbia once it enters production. In its first five years, the operation will produce 321 000 oz/y.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation