Name and Location
Agata iron/nickel laterite project, Agusan del Norte province, Philippines.

Client
The Agata project is a joint venture (JV) of TVI Pacific and 75% owner, Edmonton-based Mindoro Resources.

Project Description
The Agata project has a measured and indicated resource of 33.9-million tonnes grading 1.1% nickel and an inferred resource of two-million tonnes at 1.04% nickel.

The iron/nickel laterite project is being advanced in two stages under the JV.

The JV partners intend to develop a near-term high-iron laterite direct shipping ore (DSO) operation and a limestone DSO operation.

Later in the project’s life, the JV partners plan to build a lime plant and a nickel processing plant, for which pilot testing is under way.

Value
The Agata project will require a capital investment of about $10.1-million.

Duration
Not stated.

Latest Developments
TVI has produced nickel hydroxide product at its pilot plant.

A pregnant leach solution was passed through a counter-current ion-exchange pilot plant that recovered about 99.3% of the nickel. After dewatering, the filter cake graded between 52% and 54% nickel, which validated the company’s process and established all design parameters for the full-scale plant. TVI also produced a mixed hydroxide product grading 36% nickel, which after a two-stage precipitation step, could be upgraded to a grade of more than 40% nickel.

The final stage of pilot plant operation will comprise treating the barren solution from the ion-exchange plant to produce a disposable effluent and to perform ecological tests for residues. This will be followed by a definitive feasibility study.

Meanwhile, the feasibility study on the DSO project is nearing completion and, subject to economic viability and final permitting, will lead to the start of a DSO operation in 2014.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Mindoror Resources, tel +1 780 413 8187, fax +1 403 290 8197 or email ir@mindoro.com.
TVI Pacific, tel +1 403 265 4356, fax +1 403 264 7028 or email tvi-info@tvipacific.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

AQS Liquid Transfer
AQS Liquid Transfer

AxFlow AQS Liquid Transfer (Pty) Ltd is an Importer and Distributor of Pumps in Southern Africa

VISIT SHOWROOM 
ABB Electrification
ABB Electrification

Electrifying the world in a safe, smart, and sustainable way, ABB Electrification is a global technology leader in electrical distribution and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.05 0.725s - 111pq - 2rq
Subscribe Now