PERTH (miningweekly.com) – Junior Tietto Minerals has completed commissioning of its Abujar gold processing plant, in Côte d’Ivoire, with the project now ramping up to full production.
The 4.5-million-tonne-a-year mine is forecast to produce 200 000 oz/y of gold over the first six years of production, at an all-in cost of around $800/oz. Initially, Abujar will process lower-grade oxide ore from largely depleted artisanal mining zones prior to accessing the higher-grade fresh ore from the main pit, which is scheduled for April this year.
Tietto on Monday told shareholders that gold recoveries so far had been consistent with expectations. The company was expected to release a production guidance for 2023, and a cost guidance for the calendar year, later in April.
The openpit operation at Abujar is expected to have a mine life of over ten years, while an underground operation would extend the project life to 12 years. The addition of an underground operation is expected to add a further $48.4-million in capital costs from the beginning of year six of the operations.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation