ABM on the verge of production at Old Pirate
PERTH (miningweekly.com) – ASX-listed junior ABM Resources expects to start mining its Old Pirate gold deposit, in the Northern Territory, shortly, while the commissioning of the Coyote gold plant is expected to be completed by May.
The company told shareholders on Friday that site work was well advanced and that waste rock and the initial mining footprint areas had already been cleared, with pre-strip waste mining having started.
Some surface ore had also been moved and stockpiled on the newly formed run-of-mine pad area, with ore mining expected to start within the next three weeks.
ABM was aiming to produce between 50 000 oz and 60 000 oz of gold from the Old Pirate deposit during its first year of operation.
Pending the receipt of the final approvals, ABM would look at a staged approach for the Old Pirate project, staging capital developing and allowing for the progressive exposure of the mineral system. The miner was planning an initial five openpit operations, averaging 35 m in depth, followed by pit expansions as production continued past the first year.
ABM had reached an agreement with a subsidiary of fellow-listed Tanami Gold to lease the Coyote gold plant and infrastructure, in Western Australia, to process ore from the Old Pirate operation.
Refurbishment work on the Coyote plant had started, and was running to schedule, ABM said.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation