2Mt/y Bumi Barito coal mine to cost $75m – Cokal
PERTH (miningweekly.com) – A definitive feasibility study (DFS) for the Bumi Barito Mineral (BBM) coal project, in Indonesia, has confirmed ASX-listed Cokal’s confidence that the project could be developed at a low capital cost.
The company revealed on Thursday that a capital investment of $75-million would be required to support the two-million-tonne-a-year operation. Based on the current resource of 261-million tonnes, the project would have an estimated life of ten years.
Operating costs for the BBM project have been estimated at an average free-on-board cost of $97/t, on the basis that the mining, hauling and barging equipment would be supplied by contractors.
The project was estimated to have an after-tax net present value of $366-million and an internal rate of return of 134%.
The mine plan is based on an opencut operation, with the coal to be transported 774 km from the mine site to an ocean-going vessel at Taboneo, in the Java Sea. The transportation of the coal would involve four stages, including trucking, shallow draft barges, ocean-going barges and a floating crane transshipper to the ocean-going vessels.
The coal extracted at BBM would either be processed through a coal handling and preparation plant, or screed as direct ship product coal.
“The DFS confirms that BBM is an economically and technically robust project,” said Cokal CEO and chairperson Peter Lynch.
“We are now focused on obtaining our final forestry approval, which will enable construction to start. The approval has been progressing well and all necessary sign-offs have been obtained and it is now before the Ministry for final approval.”
Lynch added that Cokal was also in discussions with a number of parties to complete project financing.
“I am confident of unlocking further value at BBM by not only accessing a larger portion of the coal resource currently not included in the study, through efficient underground methods, but also adding to the coal resource by exploring the remaining 60% of BBM’s metallurgical coal deposit,” he said.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation