Zimplats to go ahead with $447m expansion project

2nd February 2016

By: News24Wire

  

Font size: - +

HARARE - Zimplats says it is going ahead with its Zimbabwe based projects despite continued threats on a portion of its mining lease area.

In a statement accompanying its results for the quarter ended 31 December 2015 the company said the Ngezi Phase 2 expansion project implementation is progressing well.

"A total of $447m of the project budget had been spent as at 31 December 2015," said the company adding that implementation of the outstanding components of the Phase 2 expansion project remains on schedule for overall project completion in 2016.

The company is also going ahead with refurbishment of the Selous Metallurgical Complex base metal refinery project.

"A total of $12.2m was spent on the refurbishment of the Selous Metallurgical Complex base metal refinery project and US$9.9m was committed as at 31 December 2015," said Zimplats.

The decision to refurbish the base metal refinery is in line with government's push for local beneficiation and value addition.

The company however said the impact of the declining metal prices on cash flows has resulted in the reprioritisation of capital projects with some projects being deferred to future periods.

The capital projects also come at a time the Zimbabwean government has requested the company to release land measuring 27 948 hectares for compulsory acquisition.

“On 28 December 2015 the Government of Zimbabwe wrote to the operating subsidiary requesting the release of the 27 948 hectares of ground referred to in the preliminary notice that was issued on 1 March 2013,” said Zimplats.

Zimplats has since lodged a formal objection to the preliminary notice to compulsorily acquire the land and is also seeking constructive dialogue in an endeavour to resolve the matter amicably.

Meanwhile revenue for the miner decreased by 11% from the previous quarter mainly due to the drop in metal prices compounded by a 2% decrease in 4E sales volume.

A loss from operations after royalties of $1.8m was recorded for the quarter ended 31 December 2015.

News24.com

Edited by News24Wire

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION