West African updates Sanbrado feasibility study

22nd June 2018

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – An updated feasibility study (FS) into the Sanbrado gold project, in Burkina Faso, has increased the project’s production expectations and the mine life, owner West African Resources reported on Friday.

Sanbrado is expected to produce an average of 211 000 oz/y of gold over the first five years of operation, with production averaging 133 000 oz/y over the 11-year life of mine.

The production estimate was up from the original 2017 feasibility study, which estimated that the Sanbrado project would produce about 93 000 oz/y over a nine-year mine life, producing 150 000 oz/y over the first three years of operation.

Life of mine recoveries have increased from an estimated 810 000 oz to 1.46-million ounces of gold.

The project’s estimated capital costs also increased, from the $131-million estimated in the original FS, to $185-million; however, the post tax net present value rose from $100-million to $405-million, while the post tax internal rate of return increased from 21% to 49%.

All-in sustaining costs for the life of the mine are estimated at $640/oz in the updated FS, compared with the original estimate of $759/oz.

The updated FS included a 76% increase in the probable ore reserve at Sanbrado, which is now estimated at 1.6-million ounce, and a 40% increase in the indicated resource at the M1 South deposit, which is estimated at 78 000 oz of gold.

The project is estimated to have a mineral resource of 2.35-million ounces of gold in the indicated category, and 0.55-million ounces in the inferred category.

West African MD Richard Hyde said that the updated FS confirmed that Sanbrado was a robust, hig- margin gold project.

He added that substantial upside also existed at Sanbrado, revealed by the recent high-grade intercepts beneath the reserves, which showed scope to extend the life of the M1 South deposit past four-and-a-half years.

A scoping study has also started to focus on the underground potential of the M5 deposit, while drilling at M1 South and M5 will be ongoing, with further resource and reserve updates expected by year-end.

In the meantime, Hyde said that discussions with project financiers were also under way, and the company was hoping to appoint a banking syndicate by the fourth quarter of this year.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION