Vale completes throughput test for Phase 1 of the Salobo III plant in Brazil

24th November 2023

By: Tasneem Bulbulia

Senior Contributing Editor Online

     

Font size: - +

Brazilian miner Vale has successfully completed the throughput test for the first phase of the Salobo III copper project, in the Carajás region in Brazil, with the Salobo complex exceeding an average of 32-milllion tonnes a year over a 90-day period.

This achievement is highlighted as a significant milestone under the Salobo streaming agreement with Wheaton Precious Metals. Vale in 2015 announced the by-product streaming agreement with Wheaton, which was amended this year.

In 2019, Vale started construction on the $1.1-billion Salobo III expansion project. Combined with plants I and II, throughput capacity now exceeds 32-million tonnes a year and is currently ramping up to reach full capacity of 36-milllion tonnes a year in the fourth quarter of 2024.

“The successful ramp-up of the Salobo III project represents significant growth in a top-tier operation in our energy transition metals business.

“This accomplishment is the result of enhancements to Salobo’s reliability and a steadfast commitment to operational excellence,” says Vale CEO and Vale Base Metals board director Eduardo Bartolomeo.

“Our strategic position in the Carajás region is an important lever to increase our copper production to 900 000 t/y over the next decade and deliver high-quality products to the global energy transition,” he adds.

Under the terms of the agreement with Wheaton, Salobo will receive $370-million for completion of the first phase of the Salobo III expansion project.

The remaining balance of the expansion payment will be triggered once Vale expands actual throughput above 35-million tonnes a year for a period of 90 days.

Also, Wheaton will be required to make yearly payments of between $5.1-million and $8.5-million for a ten-year period should the Salobo complex continue to produce within certain copper grades. 

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION