Richland delivers 156 000 ct in Q3 ramp-up of Capricorn mine
JOHANNESBURG (miningweekly.com) – London-listed Richland Resources has delivered 156 000 ct in the three months to September 30 as part of the production start-up and ramp-up process at its Capricorn sapphire operation, in Australia, mining and processing 21 628 t of sapphire-bearing alluvials over the three months, it said on Monday.
The company’s economical cutoff size was set at 4 mm, with smaller material being stockpiled for future sorting and grading and current cash costs estimated at less than $3/ct.
Richland concluded its first sapphire parcel sale in September, offloading 1 200 ct at $14.30/ct.
“I’m pleased with the progress achieved in the third quarter, with over 150 000 ct produced, of which more than half was produced in September following extensive work and modifications to the processing plant.
“We also achieved our first sapphire parcel sale. It should be noted that the parcel sold during late September at $14.3/ct was a customer-specific parcel and does not represent run-of-mine material,” commented CEO Bernard Olivier.
Elaborating on post-period events, he added that the company had set a fourth-quarter production target of 250 000 ct, with size and colour sorting, as well as the quality grading of the material mined during third quarter, currently being completed in preparation for a larger and ongoing parcel sales process.
“Our sales strategy currently focuses on customer-specific parcels to ensure that we get as many downstream commitments and market penetration as possible,” Olivier concluded.
Comments
The
content
you are trying to access is only available to subscribers.
If you are already a subscriber, you can Login Here.
If you are not a subscriber, you can subscribe now, by selecting one of the below options.
For more information or assistance, please contact us at subscriptions@creamermedia.co.za.
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation