Prefeasibility work progresses at Botswana copper/silver project

9th June 2017

By: Mia Breytenbach

Creamer Media Deputy Editor: Features

     

Font size: - +

Aim-listed Metal Tiger has progressed prefeasibility work at the T3 copper project, in Botswana, which it holds in joint venture (JV) with ASX-listed Mod Resources.

Key highlights of progress made includes the T3 environmental management plan (EMP) that was expected to be lodged, which should allow for the earlier advancement of the next phase of drilling at T3, the companies noted in a statement last month.

High-priority drill targets, which include two induced polarisation (IP) geophysics anomalies 800 m north of T3 and the Zone 3 mineralisation below the T3 Resource, have also been identified.

Additionally, the companies plan to start an airborne electromagnetic geophysics survey soon to identify new conductors on the T3 Dome.

“We are very pleased to report that, following consultation, the Department of Environmental Affairs has agreed that an EMP will suffice for permitting further resource drilling at T3 and the drill testing of the various exciting targets in the wider T3 area,” Metal Tiger CEO Michael McNeilly noted in a statement last month.

He added that the decision was significant, as it should allow for drilling to resume sooner than would have been required if the JV had to conduct the more detailed studies required for an environmental impact statement for the drilling permits.

“Considering the required EMP public review period, we now expect the drilling to resume in July. “[Meanwhile,] work will continue on the T3 prefeasibility study (PFS), the airborne electromagnetic geophysics survey and . . . soil sampling programmes,” he said.

The companies also looked forward to reporting on the findings of the T20 soil programme in due course.

Planned activities for the next few months also include systematic drilling of the Zone 3 mineralised contact, below the T3 Resource, as well as finalising the metallurgical, mining and processing studies for the T3 PFS.

The T3 deposit, located on the Kalahari Copper Belt, in northern Botswana, was discovered in March 2016 when a reverse- circulation drill hole intersected 52 m at 2.0% copper and 32g/t silver from shallow depth.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION