https://www.miningweekly.com

Early work starts at BP33

6th September 2023

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Box cut excavation has started at Core Lithium’s BP33 underground project, at the company’s Finniss lithium operations, in the Northern Territory.

The company is spending between A$45-million and A$50-million on early works and an updated feasibility study at BP33, with the aim of making a final investment decision (FID) on the project by the first quarter of next year.

The box cut will provide portal access from which the decline to the BP33 orebody will be developed as a part of the next phase of capital works.

“It is pleasing to see the progress of the parallel early works and feasibility study workstreams at BP33. We are aiming to make an FID for BP33 in the first quarter of 2024 and are completing these early works so we can be ready to commence decline development promptly,” said Core MD and CEO Gareth Manderson.

“We have also now commenced discussions with a number of underground mining contractors who have expressed interest in the BP33 project.

“And we are undertaking a systematic exploration programme targeting a number of deposits near the Finniss processing facilities. We are pushing ahead with drilling and updated studies at Carlton as we begin to define the optimal mine sequencing at Finniss.”

An updated feasibility study on the Carlton project, which is 2 km from the Finniss processing plant, will be completed by the end of 2024.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION