Dartbrook back in production by mid-year, says AQC
The Dartbrook coal mine, in the Hunter Valley of New South Ales, will be back in production by the middle of 2024, after 18 years in care and maintenance.
Australian Pacific Coal (AQC) is accelerating its restart works programme at the Dartbook mine, following the execution of a three-year, $60-million debt facility with Vito Asia in January.
AQC has started drawdowns from the debt facility.
“Since we announced the completion of the Dartbrook restart funding package in January, we have focused on moving the project forward on multiple fronts. With the funds now fully available for the development, orders have been placed for critical equipment and long lead items, and we have begun recruiting additional key personnel,” said interim CEO Ayten Saridas.
AQC and its partners are evaluating a range of options to accelerate the restart work programme and ramp-up period within forecast expenditure limits. The acceleration strategy is based on optimising the mine plan to allow an additional continuous miner to operate in a second panel earlier than originally planned. The modifications are expected to result in increased production in the first year and subsequent year sales volumes.
AQC said further details on the impact of that work would be announced when complete.
Encouraged by earlier studies, AQC would also further examine the potential of Dartbrook mine to produce commercial quantities of semi-soft coking coal under the current mine plan.
With met coal currently trading at a substantial premium to thermal coal, the ability to produce significant volumes of semi-soft coking coal would generate positive financial outcomes for AQC shareholders.
Meanwhile, AQC said additional working capital would be required but not until coal sales started in mid-2024. The company is working with advisers on opportunities to arrange a working capital debt facility structure of about A$30-million.
“We anticipate that sourcing a working capital facility will be relatively straightforward now that restart operations are fully funded. Vitol and our advisers have offered to assist us in this process which could open a number of doors to AQC that were previously unavailable,” said Saridas.
Comments
The
content
you are trying to access is only available to subscribers.
If you are already a subscriber, you can Login Here.
If you are not a subscriber, you can subscribe now, by selecting one of the below options.
For more information or assistance, please contact us at subscriptions@creamermedia.co.za.
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation