https://www.miningweekly.com

Big new Canada gold mine to enter production next month

16th February 2024

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

The Côté gold mine, in Sudbury, Ontario, is on the cusp of production, Toronto-listed Iamgold reported on Thursday.

The project entered 2023 with construction about 64% completed and finished the year at 98% complete, said CEO Renaud Adams, adding that production was poised to begin next month.

“While first gold is on the horizon, our primary focus and efforts are on positioning the project for a steady ramp-up of gold production through the year to achieve commercial production in the third quarter,” he said.

At steady run-rate, Cote will be the third-biggest gold mine in Canada with an expected mine life exceeding 18 years and significant opportunities for growth.

Côté will produce 495 000 oz/y at an all-in sustaining cost of $854/oz for the first six years of its mine life.

The project is owned in a 60:40 joint venture with Sumitomo Metal Mining.

Production at Côté, on a 100% basis, is expected to be between 220 000 oz and 290 000 oz next year.

This will be a significant boost to Iamgold's output, with the miner having produced 465 000 oz last year - achieving the top end of its guidance range 410 000 oz to 470 000 oz.

The majority of production in 2023 came from the Essakane mine, in Burkina Faso, with output of 372 000 oz. The Westwood mine, in Quebec, produced in excess of the top end of its guidance range of 70 000 oz to 90 000 oz with 93 000 oz produced for the year, including a record 12 400 oz in December.

Consolidated 2024 attributable gold production for Essakane and Westwood is expected to be in the range of 430 000 oz to 490 000 oz, with Essakane attributable gold production expected to be in the range of 330 000 oz to 370 000 oz and Westwood gold production expected to be in the range of 100 000 oz to 120 000 oz.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION