Bankable study confirms Nachu’s commercial viability – Magnis

31st March 2016

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – The bankable feasibility study (BFS) for the Nachu graphite project, in Tanzania, has delivered improved project economics, owner Magnis Resources revealed on Thursday.

The BFS confirmed that Magnis could develop a mine producing an average of 220 000 t/y of graphite concentrate over 15 years at a capital cost of $269-million.

The BFS estimated a net present value (NPV) of $1.69-billion and an internal rate of return (IRR) of 98%.

A 2014 prefeasibility study (PFS) estimated that the project would have a NPV of $1.04-billion and an IRR of 84%, based on a production rate of 180 000 t/y of graphite concentrate, with a mine life of 16 years. The PFS estimated capital costs of $171.4-million.

The Nachu project had a global mineral resource estimate of 174-million tonnes, grading 5.4% graphitic carbon, and represented one of the largest mineral resources of flake graphite in the world.

The mineral resource was split into five deposits, with the Block F mineral resource the primary orebody assessed in the BFS for initial production.

“The release of the BFS is another important milestone towards the development of the Nachu graphite project. It confirms that the project has outstanding projected financial returns, and details how premium graphite concentrate products of exceptional size and purity can be generated using low cost flotation processes with an exceptionally small environmental footprint,” said Magnis CEO Frank Houllis.

“These products are targeted into fast growing graphite markets such as the lithium-ion battery sector, and the BFS firmly demonstrates the commercial viability of the Nachu project to potential end-users.”

Houllis said on Thursday that Magnis was in advanced discussions with potential North American, European, Japanese and Korean customers on further cornerstone offtake agreements, while project financing discussions were progressing in parallel.

He noted that a range of financing alternatives were being considered, including the provision of senior debt.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION