PERTH (miningweekly.com) – The Queensland Resources Council on Tuesday welcomed a ruling by the Queensland Supreme Court to dismiss freight operator Aurizon’s legal challenge to a draft decision from the Queensland Competition Authority (QCA) for the future operation of the state’s major coal rail network.

Aurizon has consistently warned that the movement of up to 20-million tonnes of coal a year was in jeopardy as a result of the draft decision, with up to ten-million tonnes a year lost from the Goonyella line, up to eight-million tonnes a year from the Blackwater line, up to 1.5-million tonnes a year from the Moura line and up to 300 000 t/y from the Newlands line.

Aurizon in April launched a judicial review application of the QCA’s draft decision on the 2017 draft access undertaking for the company’s Central Queensland Coal Network (CQCN) on the basis of apprehended bias.

The company said, at the time, that the draft decision had been affected by legal error, since the QCA did not afford procedural fairness to Aurizon, owing to QCA chairperson Professor Roy Green’s conflict of interest.

In July, ten coal producers, including Anglo American, Glencore, Peabody, Yancoal and the BHP Mitsubishi Alliance, were joined as respondents to the judicial review application.

The Supreme Court on Tuesday dismissed the case, saying there was no evidence that there had been bias by Green in the QCA’s draft access undertaking, with the freight operator ordered to pay costs.

The QRC on Tuesday said the outcome was important for all Queenslanders, who are set to receive more than A$3.5-billion in coal royalties this financial year.

“The court’s decision allows the QCA to finalise its decision on the future management of the CQCN,” the QRC said.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION