Argonaut sells additional royalty on Magino

3rd November 2023

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Toronto-listed Argonaut Gold has announced the sale of an additional 1% net smelter return royalty (NSR) on the Magino mine to bolster its balance sheet following a slower-than-planned ramp-up to commercial production.

The mine, in Ontario, achieved commercial production on November 1, slightly missing the company’s original target date of September.

COO Marc Leduc explained on Thursday that plant commissioning and ramp-up proceeded largely on plan from June through August, ramping up from about 50% of nameplate capacity to 80%, placing the plant on track for commercial production in September. 

However, 20 days of unplanned downtime in September, delayed the ramp-up. This was the result of two events, the first centered on the ball mill motor drive and inching system and the second involved the semiautogenous grinding mill motor, he said.

“The EPC contractor, equipment suppliers and specialised contractors were mobilized to assist the site team in facilitating equipment repairs and address the various causes of the unplanned downtime. During commissioning, the greatest plant reliability issues centered on the process control system, which is comprised of several disparate systems.  As a result, we are systematically centralising all control functionality. The plant has been largely operating at nameplate capacity since the beginning of the quarter," Leduc continued.

Franco-Nevada and certain of its subsidiaries will acquire an additional 1% NSR on Magino and its noncore royalty holdings in Canada and Mexico for an aggregate $29.5-million.

Upon the closing of the transaction, Franco Nevada will hold an aggregate 3.0% NSR on the Magino mine.

In the third quarter, Argonaut reported consolidated gold production of 53 911 gold equivalent ounces (GEOs), including pre-commercial production of 10 693 GEOs from the Magino mine.

The company stated that full-year production for the Magino mill would not meet the guidance set out at the beginning of the year, owing to the slower-than-planned ramp-up to commercial production. However, the company remained on track to meet its consolidated production and all-in sustaining cost guidance set at the beginning of the year.  

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION