Wickepin kaolin project, Australia – update

Image of Wickepin tenements, in Western Australia

15th April 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Wickepin kaolin project.

Location
Near Wickepin, 220 km south-east of Perth, in Western Australia.

Project Owner/s
WA Kaolin.

Project Description
Wickepin is one of the biggest known remaining premium primary resources of kaolin globally and is characterised by its purity, quality and brightness.

The project currently comprises mineral resources of 644.5-million tonnes of high-grade premium kaolinised granite.

The project contains 30.5-million tonnes of kaolinised granite reserves within the mining lease, delivering a 31-year mine life.

Stage 1 is designed to develop a kaolin processing plant with a production capacity of about 200 000 t/y.

Stage 2 will increase production from 200 000 t/y to 400  000 t/y, with further modular increases to capacity to be implemented in line with market demand and funding capability.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a net present value, at a 7% discount rate, of $257-million and an internal rate of return of 47%.

Capital Expenditure
Stage 1 capital expenditure is estimated at $18.07-million, with an additional $13.57-million for Stage 2.

Planned Start/End Date
Full production at the Wickepin project is targeted for before the end of the second quarter of 2022.

Latest Developments
WA Kaolin has signed a three-year offtake agreement with a Vietnamese distributor.

Under the terms of the offtake agreement, WA Kaolin is to supply 4 500 t/y, with a minimum 2 500 t/y, for three years, starting in July of this year.

Pricing for the agreement will be competitive to the world kaolin market, delivered on a cost-and-freight basis, and pricing of at least the minimum quantity will be negotiated on a quarterly basis through mutual negotiation and agreement.

Key Contracts, Suppliers and Consultants
AUSPAN (building works).

Contact Details for Project Information
WA Kaolin, tel +61 8 9439 6300 or email asorensen@wakaolin.com.au.

Edited by Creamer Media Reporter

Comments

Showroom

Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 
ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.097 0.149s - 91pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: